View all text of Subjgrp 339 [§ 585.645 - § 585.649]

§ 585.648 - How will BOEM process my GAP?

(a) BOEM will review your submitted GAP, along with the information and certifications you submitted in compliance with § 585.646, to determine if it contains the information necessary to conduct our technical and environmental reviews.

(1) We will notify you if we deem your proposed facility or combination of facilities to be complex or significant; and

(2) We will notify you if your submitted GAP lacks any necessary information.

(b) BOEM will prepare appropriate NEPA analysis.

(c) When appropriate, we will coordinate and consult with relevant State and Federal agencies and affected federally recognized Indian Tribes and provide to other local, State, and Federal agencies and affected federally recognized Indian Tribes relevant nonproprietary data and information pertaining to your proposed activities.

(d) During the review process, we may request additional information if we determine that the information provided is not sufficient to complete the review and approval process. If you fail to provide the requested information, BOEM may disapprove your GAP.

(e) Upon completion of our technical and environmental reviews and other reviews required by Federal law (e.g., CZMA), BOEM may approve, disapprove, or approve your GAP with conditions.

(1) If we approve your GAP, we will specify terms and conditions to be incorporated into your GAP. You must certify compliance with certain of those terms and conditions, as required under 30 CFR 285.653(b); and

(2) If we disapprove your GAP, we will inform you of the reasons and allow you an opportunity to submit a revised plan addressing our concerns, and we may suspend your lease or grant, as appropriate, to give you a reasonable amount of time to resubmit the GAP.