§ 2282e. Post-authorization change reports
(a) In generalThe completion of a post-authorization change report prepared by the Corps of Engineers for a water resources development project—
(1) may not be delayed as a result of consideration being given to changes in policy or priority with respect to project consideration; and
(2) shall be submitted, upon completion, to—
(A) the Committee on Environment and Public Works of the Senate; and
(B) the Committee on Transportation and Infrastructure of the House of Representatives.
(b) Completion reviewWith respect to a post-authorization change report subject to review by the Secretary, the Secretary shall, not later than 120 days after the date of completion of such report—
(1) review the report; and
(2) provide to Congress any recommendations of the Secretary regarding modification of the applicable water resources development project.
(c) Prior reports
(d) Post-authorization change report inclusionsIn this section, the term “post-authorization change report” includes—
(1) a general reevaluation report;
(2) a limited reevaluation report; and
(3) any other report that recommends the modification of an authorized water resources development project.
(Pub. L. 114–322, title I, § 1132, Dec. 16, 2016, 130 Stat. 1653.)