§ 2743. Minor construction projects
(a) Authority
(b) Annual report
The Secretary shall submit to the congressional defense committees on an annual basis a report on each exercise of the authority in subsection (a) during the preceding fiscal year. Each report shall provide a brief description of each minor construction project covered by the report. The report shall include with respect to each project the following:
(1) The estimated original total project cost and the estimated original date of completion.
(2) The percentage of the project that is complete.
(3) The current estimated total project cost and estimated date of completion.
(c) Cost variation reports to congressional committees
(d) Notification required for certain projects
Notwithstanding subsection (a), the Secretary may not start a minor construction project with a total estimated cost of more than $5,000,000 until—
(1) the Secretary notifies the congressional defense committees of such project and total estimated cost; and
(2) a period of 15 days has elapsed after the date on which such notification is received.
(e) Minor construction project defined
(Pub. L. 107–314, div. D, title XLVII, § 4703, formerly div. C, title XXXVI, § 3622, Dec. 2, 2002, 116 Stat. 2757; renumbered div. D, title XLVII, § 4703, by Pub. L. 108–136, div. C, title XXXI, § 3141(j)(2)(A)–(C), Nov. 24, 2003, 117 Stat. 1781; Pub. L. 117–81, div. C, title XXXI, § 3115(b)(1), Dec. 27, 2021, 135 Stat. 2226; Pub. L. 117–263, div. C, title XXXI, § 3113(b), Dec. 23, 2022, 136 Stat. 3053.)