View all text of Chapter 99 [§ 7301 - § 7313]
§ 7307. National Construction Safety Team report
Not later than 90 days after completing an investigation, a Team shall issue a public report which includes—
(1) an analysis of the likely technical cause or causes of the building failure investigated;
(2) any technical recommendations for changes to or the establishment of evacuation and emergency response procedures;
(3) any recommended specific improvements to building standards, codes, and practices; and
(4) recommendations for research and other appropriate actions needed to help prevent future building failures.
(Pub. L. 107–231, § 8, Oct. 1, 2002, 116 Stat. 1475.)