§ 1604. National Forest System land and resource management plans(a) Development, maintenance, and revision by Secretary as part of program; coordination
(b) Criteria
(c) Incorporation of standards and guidelines by Secretary; time of completion; progress reports; existing management plans
(d) Public participation and consultation(1) In general
(2) No additional consultation required after approval of land management plans(A) In generalExcept as provided in subparagraph (B), notwithstanding any other provision of law, the Secretary shall not be required to engage in consultation under this section or any other provision of law (including section 7 of Public Law 93–205 (16 U.S.C. 1536) and section 402.16 of title 50, Code of Federal Regulations (or a successor regulation)) with respect to—(i) the listing of a species as threatened or endangered, or a designation of critical habitat pursuant to Public Law 93–205 (16 U.S.C. 1531 et seq.), if a land management plan has been adopted by the Secretary as of the date of listing or designation; and (ii) any provision of a land management plan adopted as described in clause (i).
(B) ExceptionSubparagraph (A) shall not apply if—(i) 15 years have passed since the date on which the Secretary adopted the land management plan described in clause (i) of that subparagraph; and
(ii) 5 years have passed since the date of enactment of this section 11 See References in Text note below.
or the date of the listing of a species as threatened or endangered for a species known to occur on the unit or the designation of critical habitat within the unit as described in clause (i) of that subparagraph, whichever is later. (C) Effect of paragraphNothing in this paragraph affects any applicable requirement of the Secretary to consult with the head of any other Federal department or agency—(i) regarding any project carried out, or proposed to be carried out, to implement a land management plan pursuant to Public Law 93–205 (16 U.S.C. 1531 et seq.), including any requirement to consult regarding the consideration of cumulative impacts of completed, ongoing, and planned projects; or (ii) with respect to—(I) the development of a modification to a land management plan; or(II) an amendment or revision to a land management plan in accordance with paragraph (4) or (5) of subsection (f).
(e) Required assurancesIn developing, maintaining, and revising plans for units of the National Forest System pursuant to this section, the Secretary shall assure that such plans—(1) provide for multiple use and sustained yield of the products and services obtained therefrom in accordance with the Multiple-Use Sustained-Yield Act of 1960 [16 U.S.C. 528–531], and, in particular, include coordination of outdoor recreation, range, timber, watershed, wildlife and fish, and wilderness; and (2) determine forest management systems, harvesting levels, and procedures in the light of all of the uses set forth in subsection (c)(1), the definition of the terms “multiple use” and “sustained yield” as provided in the Multiple-Use Sustained-Yield Act of 1960, and the availability of lands and their suitability for resource management.
(f) Required provisionsPlans developed in accordance with this section shall—(1) form one integrated plan for each unit of the National Forest System, incorporating in one document or one set of documents, available to the public at convenient locations, all of the features required by this section;
(2) be embodied in appropriate written material, including maps and other descriptive documents, reflecting proposed and possible actions, including the planned timber sale program and the proportion of probable methods of timber harvest within the unit necessary to fulfill the plan;
(3) be prepared by an interdisciplinary team. Each team shall prepare its plan based on inventories of the applicable resources of the forest;
(4) be amended in any manner whatsoever after final adoption after public notice, and, if such amendment would result in a significant change in such plan, in accordance with the provisions of subsections (e) and (f) of this section and public involvement comparable to that required by subsection (d) of this section; and
(5) be revised (A) from time to time when the Secretary finds conditions in a unit have significantly changed, but at least every fifteen years, and (B) in accordance with the provisions of subsections (e) and (f) of this section and public involvement comparable to that required by subsection (d) of this section.
(g) Promulgation of regulations for development and revision of plans; environmental considerations; resource management guidelines; guidelines for land management plansAs soon as practicable, but not later than two years after October 22, 1976, the Secretary shall in accordance with the procedures set forth in section 553 of title 5, promulgate regulations, under the principles of the Multiple-Use Sustained-Yield Act of 1960 [16 U.S.C. 528–531] that set out the process for the development and revision of the land management plans, and the guidelines and standards prescribed by this subsection. The regulations shall include, but not be limited to—(1) specifying procedures to insure that land management plans are prepared in accordance with the National Environmental Policy Act of 1969 [42 U.S.C. 4321 et seq.], including, but not limited to, direction on when and for what plans an environmental impact statement required under section 102(2)(C) of that Act [42 U.S.C. 4332(2)(C)] shall be prepared; (2) specifying guidelines which—(A) require the identification of the suitability of lands for resource management;
(B) provide for obtaining inventory data on the various renewable resources, and soil and water, including pertinent maps, graphic material, and explanatory aids; and
(C) provide for methods to identify special conditions or situations involving hazards to the various resources and their relationship to alternative activities;
(3) specifying guidelines for land management plans developed to achieve the goals of the Program which—(A) insure consideration of the economic and environmental aspects of various systems of renewable resource management, including the related systems of silviculture and protection of forest resources, to provide for outdoor recreation (including wilderness), range, timber, watershed, wildlife, and fish;
(B) provide for diversity of plant and animal communities based on the suitability and capability of the specific land area in order to meet overall multiple-use objectives, and within the multiple-use objectives of a land management plan adopted pursuant to this section, provide, where appropriate, to the degree practicable, for steps to be taken to preserve the diversity of tree species similar to that existing in the region controlled by the plan;
(C) insure research on and (based on continuous monitoring and assessment in the field) evaluation of the effects of each management system to the end that it will not produce substantial and permanent impairment of the productivity of the land;
(D) permit increases in harvest levels based on intensified management practices, such as reforestation, thinning, and tree improvement if (i) such practices justify increasing the harvests in accordance with the Multiple-Use Sustained-Yield Act of 1960, and (ii) such harvest levels are decreased at the end of each planning period if such practices cannot be successfully implemented or funds are not received to permit such practices to continue substantially as planned;
(E) insure that timber will be harvested from National Forest System lands only where—(i) soil, slope, or other watershed conditions will not be irreversibly damaged;
(ii) there is assurance that such lands can be adequately restocked within five years after harvest;
(iii) protection is provided for streams, streambanks, shorelines, lakes, wetlands, and other bodies of water from detrimental changes in water temperatures, blockages of water courses, and deposits of sediment, where harvests are likely to seriously and adversely affect water conditions or fish habitat; and
(iv) the harvesting system to be used is not selected primarily because it will give the greatest dollar return or the greatest unit output of timber; and
(F) insure that clearcutting, seed tree cutting, shelterwood cutting, and other cuts designed to regenerate an evenaged stand of timber will be used as a cutting method on National Forest System lands only where—(i) for clearcutting, it is determined to be the optimum method, and for other such cuts it is determined to be appropriate, to meet the objectives and requirements of the relevant land management plan;
(ii) the interdisciplinary review as determined by the Secretary has been completed and the potential environmental, biological, esthetic, engineering, and economic impacts on each advertised sale area have been assessed, as well as the consistency of the sale with the multiple use of the general area;
(iii) cut blocks, patches, or strips are shaped and blended to the extent practicable with the natural terrain;
(iv) there are established according to geographic areas, forest types, or other suitable classifications the maximum size limits for areas to be cut in one harvest operation, including provision to exceed the established limits after appropriate public notice and review by the responsible Forest Service officer one level above the Forest Service officer who normally would approve the harvest proposal: Provided, That such limits shall not apply to the size of areas harvested as a result of natural catastrophic conditions such as fire, insect and disease attack, or windstorm; and
(v) such cuts are carried out in a manner consistent with the protection of soil, watershed, fish, wildlife, recreation, and esthetic resources, and the regeneration of the timber resource.
(h) Scientific committee to aid in promulgation of regulations; termination; revision committees; clerical and technical assistance; compensation of committee members(1) In carrying out the purposes of subsection (g) of this section, the Secretary shall appoint a committee of scientists who are not officers or employees of the Forest Service. The committee shall provide scientific and technical advice and counsel on proposed guidelines and procedures to assure that an effective interdisciplinary approach is proposed and adopted. The committee shall terminate upon promulgation of the regulations, but the Secretary may, from time to time, appoint similar committees when considering revisions of the regulations. The views of the committees shall be included in the public information supplied when the regulations are proposed for adoption.
(2) Clerical and technical assistance, as may be necessary to discharge the duties of the committee, shall be provided from the personnel of the Department of Agriculture.
(3) While attending meetings of the committee, the members shall be entitled to receive compensation at a rate of $100 per diem, including traveltime, and while away from their homes or regular places of business they may be allowed travel expenses, including per diem in lieu of subsistence, as authorized by section 5703 of title 5, for persons in the Government service employed intermittently.
(i) Consistency of resource plans, permits, contracts, and other instruments with land management plans; revision
(j) Effective date of land management plans and revisions
(k) Development of land management plans
(l) Program evaluation; process for estimating long-term costs and benefits; summary of data included in annual reportThe Secretary shall—(1) formulate and implement, as soon as practicable, a process for estimating long-terms 22 So in original. Probably should be “long-term”.
costs and benefits to support the program evaluation requirements of this subchapter. This process shall include requirements to provide information on a representative sample basis of estimated expenditures associated with the reforestation, timber stand improvement, and sale of timber from the National Forest System, and shall provide a comparison of these expenditures to the return to the Government resulting from the sale of timber; and (2) include a summary of data and findings resulting from these estimates as a part of the annual report required pursuant to section 1606(c) of this title, including an identification on a representative sample basis of those advertised timber sales made below the estimated expenditures for such timber as determined by the above cost process; and 33 So in original. The “; and” probably should be a period.
(m) Establishment of standards to ensure culmination of mean annual increment of growth; silvicultural practices; salvage harvesting; exceptionsThe Secretary shall establish—(1) standards to insure that, prior to harvest, stands of trees throughout the National Forest System shall generally have reached the culmination of mean annual increment of growth (calculated on the basis of cubic measurement or other methods of calculation at the discretion of the Secretary): Provided, That these standards shall not preclude the use of sound silvicultural practices, such as thinning or other stand improvement measures: Provided further, That these standards shall not preclude the Secretary from salvage or sanitation harvesting of timber stands which are substantially damaged by fire, windthrow or other catastrophe, or which are in imminent danger from insect or disease attack; and
(2) exceptions to these standards for the harvest of particular species of trees in management units after consideration has been given to the multiple uses of the forest including, but not limited to, recreation, wildlife habitat, and range and after completion of public participation processes utilizing the procedures of subsection (d) of this section.
(Pub. L. 93–378, § 6, formerly, § 5, Aug. 17, 1974, 88 Stat. 477, renumbered § 6 and amended Pub. L. 94–588, §§ 2, 6, 12(a), Oct. 22, 1976, 90 Stat. 2949, 2952, 2958; Pub. L. 115–141, div. O, title II, § 208(a), (b)(2), Mar. 23, 2018, 132 Stat. 1065, 1066.)