View all text of Subpart 228.1 [228.102 - 228.106-7]
228.102-1 - 228.102-1 General.
The requirement for performance and payment bonds is waived for cost-reimbursement contracts. However, for cost-type contracts with fixed-price construction subcontracts over $40,000, require the prime contractor to obtain from each of its construction subcontractors performance and payment protections in favor of the prime contractor as follows:
(1) For fixed-price construction subcontracts over $40,000, but not exceeding $150,000, payment protection sufficient to pay labor and material costs, using any of the alternatives listed at FAR 28.102-1(b)(1).
(2) For fixed-price construction subcontracts over $150,000—
(i) A payment bond sufficient to pay labor and material costs; and
(ii) A performance bond in an equal amount if available at no additional cost.