View all text of Subpart 1309.4 [1309.403 - 1309.407-3]
1309.405-1 - 1309.405-1 Continuation of current contracts.
(a) The designee authorized to direct the discontinuance of a contract or subcontract because of a debarment, suspension or proposed debarment is set forth in CAM 1301.70.
(b) A written determination must be issued by the designee authorized in CAM 1301.70 before the following actions can be taken with a contractor that is debarred, suspended or proposed for debarment:
(1) Place any orders exceeding the maximum on an indefinite delivery contract;
(2) Place orders under Federal supply schedule contracts, blanket purchase orders or basic ordering agreements; or
(3) Add new work or exercise options that extend the duration of a current contract or order.