View all text of Subpart 54.05 [§ 54.05-1 - § 54.05-30]
§ 54.05-15 - Weldment toughness tests—procedure qualifications.
(a) Plate for which Charpy V-notch impact testing is required in the parent material and for which V-notch minima are specified must similarly have welding procedures qualified for toughness by Charpy V-notch testing. For these tests, the test plates must be oriented with their final rolling direction parallel to the weld axis (i.e., so that transverse impact specimens result), and with the V-notch normal to the plate surface. The sample weld joint preparation must be the same as that used in production. The number of test specimens and the location of their notches must be as shown in Figure 1 to § 54.05-15(a) and as described in paragraphs (a)(1) through (5) of this section.
(1) Three specimens with the notch centered in the weld metal.
(2) Three specimens with the notch centered on the fusion line between parent plate and weld. (The fusion line may be identified by etching the specimen with a mild reagent.)
(3) Three specimens with the notch centered in the heat affected zone, 1 mm from the fusion line.
(4) Same as paragraph (a)(3) of this section, but 3 mm from the fusion line.
(5) Same as paragraph (a)(3) of this section, but 5 mm from the fusion line.
Figure 1 to § 54.05-15(a)—Charpy V-Notch Specimen Removal Details(b) Plate materials for which Charpy V-notch minimums are not specified, or for which a Charpy V-notch correlation with NDT is not known, and which are themselves tested for toughness by the drop-weight procedure, must have welding procedures similarly qualified by the drop-weight test. For such qualifications, two drop-weight specimens are to be tested, with the notch positioned directly above and parallel to the centerline of the weld.
(c) Piping welding toughness tests must be qualified, by making Charpy V-notch impact tests as prescribed in paragraph (a) of this section.
(d) Materials which are specially approved based on toughness criteria or tests, other than those discussed in paragraphs (a) and (b) of this section, must have welding procedures tested and qualified for toughness as deemed appropriate and necessary by the Commandant.
(e) In the case of stainless steels, weld procedure toughness tests may be limited to weld metal only if this is all that is required by § 54.25-15.