View all text of Subpart 3179 [§ 3179.1 - § 3179.200]
§ 3179.43 - Data submission and notification requirements.
(a) Table 1 is a summary of the Sundry Notice requirements in this subpart.
Table 1 to Paragraph
Sundry notice requirements | Reference | Flaring of gas following removal of ≥50 percent of the natural gas liquids from the gas stream on-lease | § 3179.41(b)(12). | Other gas sample location for flare approved by the AO | § 3179.71(d)(3) and (e)(2). | Unavoidable/avoidable determination of loss of oil and/or gas while drilling for loss of well control event | § 3179.80. | Extension of time limit or volumetric limit for well completion or recompletion flaring, or exploratory coalbed methane dewatering flaring | § 3179.81(e). | Extension of time limit for well testing subsequent to initial completion | § 3179.82. | Within 45 days of start of an emergency, estimate the volume flared or vented beyond the first 48 hours of the emergency | § 3179.83(c). | Delay of leak repair beyond 30 calendar days with good cause | § 3179.101(b). |
---|
(b) Table 2 summarizes the locations in this subpart that require an operator to provide information to the authorized officer upon request.
Table 2 to Paragraph
Information required at the request of the AO | Reference | Ultrasonic meter flare gas testing report | § 3179.71(c)(2)(i). | Ultrasonic meter manufacturer's specifications including installation and operation specifications | § 3179.71(c)(2)(ii). | Recordkeeping for vented or flared gas events | § 3179.72(c). | Recordkeeping for leak detection and repair | § 3179.102(a). |
---|
(c) Table 3 summarizes the initial LDAR program submission and subsequent annual reporting.
Table 3 to Paragraph (
Information required to be sent to the BLM State Office | Reference | First submission of a leak detection and repair program to the BLM for review | § 3179.100(b) and (d). | Annual review and update of the leak detection and repair program to the BLM | § 3179.100(e). |
---|