- Table 37 to Subpart UUU of Part 63—Requirements for Performance Tests for Bypass Lines

As stated in § 63.1569(b)(1), you shall meet each requirement in the following table that applies to you.

For this standard . . . You shall . . . 1. Option 1: Install and operate a flow indicator, level recorder, or electronic valve position monitor.Record during the performance test for each type of control device whether the flow indicator, level recorder, or electronic valve position monitor was operating and whether flow was detected at any time during each hour of level the three runs comprising the performance test.
[67 FR 17773, Apr. 11, 2002, as amended at 70 FR 6942, Feb. 9, 2005]