- Table 2 to Subpart JJJJ of Part 63—Applicability of 40 CFR Part 63 General Provisions to Subpart JJJJ
You must comply with the applicable General Provisions requirements according to the following table:
General provisions reference | Applicable to subpart JJJJ | Explanation | § 63.1(a)(1)-(4) | Yes | § 63.1(a)(5) | No | Reserved. | § 63.1(a)(6)-(8) | Yes | § 63.1(a)(9) | No | Reserved. | § 63.1(a)(10)-(14) | Yes | § 63.1(b)(1) | No | Subpart JJJJ specifies applicability. | § 63.1(b)(2)-(3) | Yes | § 63.1(c)(1) | Yes | § 63.1(c)(2) | No | Area sources are not subject to emission standards of subpart JJJJ. | § 63.1(c)(3) | No | Reserved. | § 63.1(c)(4) | Yes | § 63.1(c)(5) | Yes | § 63.1(c)(6) | Yes | § 63.1(d) | No | Reserved. | § 63.1(e) | Yes | § 63.2 | Yes | Additional definitions in subpart JJJJ. | § 63.3(a)-(c) | Yes | § 63.4(a)(1)-(3) | Yes | § 63.4(a)(4) | No | Reserved. | § 63.4(a)(5) | Yes | § 63.4(b)-(c) | Yes | § 63.5(a)(1)-(2) | Yes | § 63.5(b)(1) | Yes | § 63.5(b)(2) | No | Reserved. | § 63.5(b)(3)-(6) | Yes | § 63.5(c) | No | Reserved. | § 63.5(d) | Yes | § 63.5(e) | Yes | § 63.5(f) | Yes | § 63.6(a) | Yes | Applies only when capture and control system is used to comply with the standard. | § 63.6(b)(1)-(5) | No | § 63.3330 specifies compliance dates. | § 63.6(b)(6) | No | Reserved. | § 63.6(b)(7) | Yes | § 63.6(c)(1)-(2) | Yes | § 63.6(c)(3)-(4) | No | Reserved. | § 63.6(c)(5) | Yes | § 63.6(d) | No | Reserved. | § 63.6(e)(1)(i) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019, see § 63.3340(a) for general duty requirement. Yes, for all other affected sources before July 9, 2021, and No thereafter, see § 63.3340(a) for general duty requirement. | § 63.6(e)(1)(ii) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.6(e)(1)(iii) | Yes | § 63.6(e)(2) | No | Reserved. | § 63.6(e)(3) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.6(f)(1) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.6(f)(2)-(3) | Yes | § 63.6(g) | Yes | § 63.6(h) | No | Subpart JJJJ does not require continuous opacity monitoring systems (COMS). | § 63.6(i)(1)-(14) | Yes | § 63.6(i)(15) | No | Reserved. | § 63.6(i)(16) | Yes | § 63.6(j) | Yes | § 63.7(a)-(d) | Yes | § 63.7(e)(1) | No | See § 63.3360(e)(2). | § 63.7(e)(2)-(3) | Yes | § 63.7(f)-(h) | Yes | § 63.8(a)(1)-(2) | Yes | § 63.8(a)(3) | No | Reserved. | § 63.8(a)(4) | No | Subpart JJJJ does not have monitoring requirements for flares. | § 63.8(b) | Yes | § 63.8(c)(1) and § 63.8(c)(1)(i) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019, see § 63.3340(a) for general duty requirement. Yes, for all other affected sources before July 9, 2021, and No thereafter, see § 63.3340(a) for general duty requirement. | § 63.8(c)(1)(ii) | Yes | § 63.8(c)(1)(ii) only applies if you use capture and control systems. | § 63.8(c)(1)(iii) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.8(c)(2)-(3) | Yes | See § 63.3350(e)(10)(iv) for temperature sensor validation procedures | § 63.8(c)(4) | No | § 63.3350 specifies the requirements for the operation of CMS for capture systems and add-on control devices at sources using these to comply. | § 63.8(c)(5) | No | Subpart JJJJ does not require COMS. | § 63.8(c)(6)-(8) | Yes | Provisions for COMS are not applicable. | § 63.8(d)(1)-(2) | Yes | Refer to § 63.3350(e)(5) for CPMS quality control procedures to be included in the quality control program. | § 63.8(d)(3) | No | § 63.3350(e)(5) specifies the program of corrective action. | § 63.8(e)-(f) | Yes | § 63.8(e)(2) does not apply to CPMS. § 63.8(f)(6) only applies if you use CEMS. | § 63.8(g) | Yes | Only applies if you use CEMS. | § 63.9(a) | Yes | § 63.9(b)(1) | Yes | § 63.9(b)(2) | Yes | Except § 63.3400(b)(1) requires submittal of initial notification for existing affected sources no later than 1 year before compliance date. | § 63.9(b)(3)-(5) | Yes | § 63.9(c)-(e) | Yes | § 63.9(f) | No | Subpart JJJJ does not require opacity and visible emissions observations. | § 63.9(g) | Yes | Provisions for COMS are not applicable. | § 63.9(h)(1)-(3) | Yes | § 63.9(h)(4) | No | Reserved. | § 63.9(h)(5)-(6) | Yes | § 63.9(i) | Yes | § 63.9(j) | Yes | § 63.9(k) | Yes | Only as specified in § 63.9(j). | § 63.10(a) | Yes | § 63.10(b)(1) | Yes | § 63.10(b)(2)(i) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.10(b)(2)(ii) | No | See § 63.3410 for recordkeeping of relevant information. | § 63.10(b)(2)(iii) | Yes | § 63.10(b)(2)(iii) only applies if you use a capture and control system. | § 63.10(b)(2)(iv)-(v) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.10(b)(2)(vi)-(xiv) | Yes | § 63.10(b)(3) | Yes | § 63.10(c)(1) | Yes | § 63.10(c)(2)-(4) | No | Reserved. | § 63.10(c)(5)-(8) | Yes | § 63.10(c)(9) | No | Reserved. | § 63.10(c)(10)-(14) | Yes | § 63.10(c)(15) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. | § 63.10(d)(1)-(2) | Yes | § 63.10(d)(3) | No | Subpart JJJJ does not require opacity and visible emissions observations. | § 63.10(d)(4) | Yes | § 63.10(d)(5)(i) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. See § 63.3400(c) for malfunction reporting requirements. | § 63.10(d)(5)(ii) | Depends, see explanation | No, for new or reconstructed sources which commenced construction or reconstruction after September 19, 2019. Yes, for all other affected sources before July 9, 2021, and No thereafter. See § 63.3400(c) for malfunction reporting requirements. | § 63.10(e)(1)-(2) | Yes | Provisions for COMS are not applicable. | § 63.10(e)(3)-(4) | No | Subpart JJJJ does not require opacity and visible emissions observations. | § 63.10(f) | Yes | § 63.11 | No | Subpart JJJJ does not specify use of flares for compliance. | § 63.12 | Yes | § 63.13 | Yes | § 63.14 | Yes | Subpart JJJJ includes provisions for alternative ASME and ASTM test methods that are incorporated by reference. | § 63.15 | Yes | § 63.16 | Yes |
---|