View all text of Subjgrp 172 [§ 154.2100 - § 154.2113]
§ 154.2106 - Detonation arresters installation.
This section applies only to facilities collecting vapors of flammable, combustible, or non-high flash point liquid cargoes.
(a) Detonation arresters must be installed in accordance with the guidelines outlined in the arrester manufacturer's acceptance letter provided by the Coast Guard.
(b) On either side of a detonation arrester, line size expansions must be in a straight pipe run and must be no closer than 120 times the pipe's diameter from the detonation arrester unless the manufacturer has test data to show the expansion can be closer.