View all text of Subjgrp 180 [§ 285.1018 - § 285.1019]
§ 285.1019 - What are the decommissioning requirements for an Alternate Use RUE?
(a) Decommissioning requirements will be determined by BOEM and BSEE on a case-by-case basis, and will be included in the terms of the Alternate Use RUE.
(b) Decommissioning activities must be completed within 1 year of termination of the Alternate Use RUE.
(c) If you fail to satisfy all decommissioning requirements within the prescribed time period, BOEM will call for the forfeiture of your bond or other financial guarantee, and you will remain liable for all accidents or damages that might result from such failure.