View all text of Subjgrp 176 [§ 285.912 - § 285.912]
§ 285.912 - After I remove a facility, cable, or pipeline, what information must I submit?
Within 60 days after you remove a facility, cable, or pipeline, you must submit a written report to BSEE that includes the following:
(a) A summary of the removal activities, including the date they were completed;
(b) A description of any mitigation measures you took; and
(c) If you used explosives, a statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the facility were consistent with those in the approved decommissioning application.