View all text of Subjgrp 164 [§ 285.631 - § 285.649]
§ 285.632 - What documents must I submit before I may construct and install facilities under my approved COP?
(a) You must submit to BSEE the documents listed in the following table:
Document: | Requirements are found in: | (1) Facility Design Report | § 285.701 | (2) Fabrication and Installation Report | § 285.702 |
---|
(b) You must submit your safety management system, as required by § 285.810.
(c) These activities must fall within the scope of your approved COP. If they do not fall within the scope of your approved COP, you will be required to submit a revision to your COP, under 30 CFR 585.634, for BOEM approval before commencing the activity.