§ 635.307 - Coordination.
(a) The right-of-way clearance, utility, and railroad work are to be so coordinated with the physical construction that no unnecessary delay or cost for the physical construction will occur.
(b) All right-of-way clearance, utility, and railroad work performed separately from the contract for the physical construction of the project are to be accomplished in accordance with provisions of the following:
(1) 23 CFR part 140, subpart I;
(2) 23 CFR part 646, subpart B;
(3) 23 CFR 710.403; and
(4) 23 CFR part 645, subpart A.