Appendix B - Appendix B to Part 603—Flow Down Requirements for Purchases of Goods and Services

A. As discussed in § 603.705, the contracting officer must inform recipients of any requirements that flow down to their purchases of goods or services (e.g., supplies or equipment) under their TIA. Note that purchases of goods or services differ from subawards, which are for substantive RD&D program performance.

B. Appendix A to 10 CFR part 600, subpart D lists eight requirements that commonly apply to firms' purchases under grants or cooperative agreements. Of those eight, two that apply to all recipients' purchases under a TIA are:

1. Byrd Anti-Lobbying Amendment (31 U.S.C. 1352). A contractor submitting a bid to the recipient for a contract award of $100,000 or more must file a certification with the recipient that it has not and will not use Federal appropriations for certain lobbying purposes. The contractor also must disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. For further details, see 10 CFR part 601, the DOE's codification of the Government-wide common rule implementing this amendment.

2. Debarment and suspension. Recipients may not make contract awards that exceed the simplified acquisition threshold (currently $100,000) and certain other contract awards may not be made to parties listed on the General Services Administration (GSA) “List of Parties Excluded from Federal Procurement and Nonprocurement Programs.” The GSA list contains the names of parties debarred, suspended, or otherwise excluded by agencies, and parties declared ineligible under statutory or regulatory authority other than Executive Orders 12549 (3 CFR, 1986 Comp., p. 189) and 12689 (3 CFR, 1989 Comp., p. 235). For further details, see subparts A through E of 10 CFR part 606, which is the DOE's codification of the Government-wide common rule implementing Executive Orders 12549 and 12689.

C. One other requirement applies only in cases where construction work is to be performed under the TIA with Federal funds or recipient funds counted toward required cost sharing:

1. Equal Employment Opportunity. If the TIA includes construction work, the contracting officer should inform the recipient that Department of Labor regulations at 41 CFR 60-1.4(b) prescribe a clause that must be incorporated into construction awards and subawards. Further details are provided in Appendix B to 10 CFR 600 subpart D, item 1.