View all text of Subjgrp 45 [§ 603.560 - § 603.565]

§ 603.565 - Use of a hybrid instrument.

For a RD&D project that is to be carried out by a number of participants, the contracting officer may award a TIA that provides for some participants to perform under fixed-support arrangements and others to perform under expenditure-based arrangements. This approach may be useful, for example, if a commercial firm that is a participant will not accept an agreement with all of the post-award requirements of an expenditure-based award. Before using a fixed-support arrangement for that firm's portion of the project, the agreement must meet the criteria in § 603.305.