View all text of Subjgrp 130 [§ 250.1725 - § 250.1731]

§ 250.1729 - After I remove a platform or other facility, what information must I submit?

Within 30 days after you remove a platform or other facility, you must submit a written report to the Regional Supervisor that includes the following:

(a) A summary of the removal operation including the date it was completed;

(b) A description of any mitigation measures you took; and

(c) A statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the platform or other facility were consistent with those set forth in the approved removal application.