View all text of Subjgrp 88 [§ 250.410 - § 250.418]

§ 250.418 - What additional information must I submit with my APD?

You must include the following with the APD:

(a) Rated capacities of the drilling rig and major drilling equipment, if not already on file with the appropriate District office;

(b) A drilling fluids program that includes the minimum quantities of drilling fluids and drilling fluid materials, including weight materials, to be kept at the site;

(c) A proposed directional plot if the well is to be directionally drilled;

(d) A Hydrogen Sulfide Contingency Plan (see § 250.490), if applicable, and not previously submitted;

(e) A welding plan (see §§ 250.109 to 250.113) if not previously submitted;

(f) In areas subject to subfreezing conditions, evidence that the drilling equipment, BOP systems and components, diverter systems, and other associated equipment and materials are suitable for operating under such conditions;

(g) A request for approval, if you plan to wash out or displace cement to facilitate casing removal upon well abandonment. Your request must include a description of how far below the mudline you propose to displace cement and how you will visually monitor returns;

(h) Certification of your casing and cementing program as required in § 250.420(a)(7); and

(i) Such other information as the District Manager may require.

(j) For Arctic OCS exploratory drilling operations, you must provide the information required by § 250.470.

[76 FR 64462, Oct. 18, 2011, as amended at 77 FR 50892, Aug. 22, 2012; 81 FR 26018, Apr. 29, 2016; 81 FR 46561, July 15, 2016]