Collapse to view only 234.005-1 - 234.005-1 Competition.

234.001 - 234.001 Definitions.

As used in this subpart—

Acceptable earned value management system and earned value management system are defined in the clause at 252.234-7002, Earned Value Management System.

Production of major defense acquisition program means the production and deployment of a major system that is intended to achieve an operational capability that satisfies mission needs, or an activity otherwise defined as Milestone C under Department of Defense Instruction 5000.02 or related authorities.

Significant deficiency is defined in the clause at 252.234-7002, Earned Value Management System, and is synonymous with noncompliance.

[76 FR 28867, May 18, 2011, as amended at 79 FR 4632, Jan. 29, 2014]

234.003 - 234.003 Responsibilities.

DoDD 5000.01, The Defense Acquisition System, and DoDI 5000.02, Operation of the Adaptive Acquisition Framework, contain the DoD implementation of OMB Circular A-109 and OMB Circular A-11.

[70 FR 14575, Mar. 23, 2005, as amended at 76 FR 76320, Dec. 7, 2011; 88 FR 80466, Nov. 17, 2023]

234.004 - 234.004 Acquisition strategy.

(1) See 209.570 for policy applicable to acquisition strategies that consider the use of lead system integrators.

(2) Contract type.

(i) In accordance with section 818 of the National Defense Authorization Act for Fiscal Year 2007 (Pub. L. 109-364), for major defense acquisition programs at Milestone B—

(A) The milestone decision authority shall select, with the advice of the contracting officer, the contract type for a development program at the time of Milestone B approval or, in the case of a space program, Key Decision Point B approval;

(B) The basis for the contract type selection shall be documented in the acquisition strategy. The documentation—

(1) Shall include an explanation of the level of program risk; and

(2) If program risk is determined to be high, shall outline the steps taken to reduce program risk and the reasons for proceeding with Milestone B approval despite the high level of program risk; and

(C) If a cost-reimbursement type contract is selected, the contract file shall include the milestone decision authority's written determination that—

(1) The program is so complex and technically challenging that it would not be practicable to reduce program risk to a level that would permit the use of a fixed-price type contract; and

(2) The complexity and technical challenge of the program is not the result of a failure to meet the requirements of 10 U.S.C. 4251.

(ii) In accordance with section 811 of the National Defense Authorization Act for Fiscal Year 2013 (Pub. L. 112-239), the contracting officer shall—

(A) Not use cost-reimbursement line items for the acquisition of production of major defense acquisition programs, unless the Under Secretary of Defense for Acquisition and Sustainment (USD(A&S)), or the milestone decision authority when the milestone decision authority is the service acquisition executive of the military department that is managing the program, submits to the congressional defense committees—

(1) A written certification that the particular cost-reimbursement line items are needed to provide a required capability in a timely and cost effective manner; and

(2) An explanation of the steps taken to ensure that cost-reimbursement line items are used only to achieve the purposes of the exception; and

(B) Include a copy of such congressional certification in the contract file.

(iii) See 216.301-3 for additional contract type approval requirements for cost-reimbursement contracts.

(iv) For fixed-price incentive (firm target) contracts, contracting officers shall comply with the guidance provided at PGI 216.403-1(1)(ii)(B) and (C).

(v) In accordance with section 808 of the National Defense Authorization Act for Fiscal Year 2023 (Pub. L. 117-263)—

(A) The contracting officer shall not procure more than one lot for low-rate initial production, as defined at 10 U.S.C. 4231, associated with a major defense acquisition program if—

(1) The milestone decision authority authorizes the use of a fixed-price type contract at the time of Milestone B approval; and

(2) The scope of work of the fixed-price type contract includes both the development and low-rate initial production of items for such major defense acquisition program; and

(B) This limitation may be waived by the service acquisition executive for the department concerned, delegable to no lower than one level above the contracting officer, if—

(1) A written notification of the waiver, including associated rationale, is provided to the congressional defense committees no later than 30 days after issuance of the waiver in accordance with agency procedures; and

(2) A copy of the waiver and such congressional notification are included in the contract file.

(3) The contracting officer shall include in solicitations for contracts for the technical maturation and risk reduction phase, engineering and manufacturing development phase or production phase of a weapon system, including embedded software—

(i) Clearly defined measurable criteria for engineering activities and design specifications for reliability and maintainability provided by the program manager, or the comparable requiring activity official performing program management responsibilities; or

(ii) Ensure a copy of the justification, executed by the program manager or the comparable requiring activity official performing program management responsibilities for the decision that engineering activities and design specifications for reliability and maintainability should not be a requirement, is included in the contract file (10 U.S.C. 4328).

[73 FR 4118, Jan. 24, 2008, as amended at 79 FR 4632, Jan. 29, 2014; 79 FR 23278, Apr. 28, 2014; 79 FR 58694, Sept. 30, 2014; 84 FR 58334, Oct. 31, 2019, 84 FR 65307, Nov. 27, 2019; 87 FR 76995, Dec. 16, 2022; 88 FR 55940, Aug. 17, 2023; 89 FR 31657, Apr. 25, 2024]

234.005 - 234.005 General requirements.

234.005-1 - 234.005-1 Competition.

A contract that is initially awarded from the competitive selection of a proposal resulting from a broad agency announcement (see 235.016) may contain a contract line item or contract option using funds not limited to those identified in 235.016 for the development and demonstration or initial production of technology developed under the contract, or the delivery of initial or additional items if the item or a prototype thereof is created as the result of work performed under the contract, only when it adheres to the following limitations:

(1) The contract line item or contract option shall be limited to the delivery of the minimal amount of initial or additional items or prototypes that will allow for timely competitive solicitation and award of a follow-on development or production contract for those items.

(2) The term of the contract line item or contract option shall be for not more than 2 years.

(3) The dollar value of the work to be performed pursuant to the contract line item or contract option shall not exceed $100 million in fiscal year 2017 constant dollars. (10 U.S.C. 4004)

(4) See PGI 234.005-1 for guidance on providing, upon request, the benefits derived from use of this competitive selection method.

[75 FR 32639, June 8, 2010, as amended at 81 FR 17045, Mar. 25, 2016; 84 FR 4365, Feb. 15, 2019; 87 FR 25145, Apr. 28, 2022; 87 FR 76995, Dec. 16, 2022; 88 FR 80466, Nov. 17, 2023]

234.005-2 - 234.005-2 Mission-oriented solicitation.

See 215.101-2-70(b)(2) for the prohibition on the use of the lowest price technically acceptable source selection process for engineering and manufacturing development of a major defense acquisition program for which budgetary authority is requested beginning in fiscal year 2019.

[84 FR 50789, Sept. 26, 2019]

234.2 - Subpart 234.2—Earned Value Management System

234.70 - Subpart 234.70—Acquisition of Major Weapon Systems as Commercial Products

234.71 - Subpart 234.71—Cost and Software Data Reporting