Collapse to view only 206.001-70 - 206.001-70 Exception for prototype projects for follow-on production contracts.

206.000 - 206.000 Scope of part.

For information on the various approaches that may be used to competitively fulfill DoD requirements, see PGI 206.000.

[80 FR 21657, Apr. 20, 2015]

206.001 - 206.001 Applicability.

(b) As authorized by 10 U.S.C. 1091, contracts awarded to individuals using the procedures at 237.104(b)(ii) are exempt from the competitive requirements of FAR part 6.

[70 FR 2361, Jan. 13, 2005, as amended at 87 FR 10990, Feb. 28, 2022]

206.001-70 - 206.001-70 Exception for prototype projects for follow-on production contracts.

(a) Also excepted from this part are follow-on production contracts for products developed pursuant to the “other transactions” authority of 10 U.S.C. 4022 for prototype projects, when the contracting officer receives sufficient documentation from the agreements officer issuing the other transaction agreement for the prototype project that—

(1) The other transaction agreement included provisions for a follow-on production contract (10 U.S.C. 4022(f)(1)); and

(2) Where applicable, the threshold at 10 U.S.C. 4022(a)(2)(C) and the requirements at 10 U.S.C. 4022(f)(2)(A) and (B) have been met.

(b) See PGI 206.001-70 for additional guidance.

[88 FR 33835, May 25, 2023]

206.1 - Subpart 206.1—Full and Open Competition

206.2 - Subpart 206.2—Full and Open Competition After Exclusion of Sources

206.3 - Subpart 206.3—Other Than Full and Open Competition