Collapse to view only § 63.11088 - What requirements must I meet for gasoline loading racks if my facility is a bulk gasoline terminal?

What This Subpart Covers

§ 63.11080 - What is the purpose of this subpart?

This subpart establishes national emission limitations and management practices for hazardous air pollutants (HAP) emitted from area source gasoline distribution bulk terminals, bulk plants, and pipeline facilities. This subpart also establishes requirements to demonstrate compliance with the emission limitations and management practices.

§ 63.11081 - Am I subject to the requirements in this subpart?

(a) The affected source to which this subpart applies is each area source bulk gasoline terminal, pipeline breakout station, pipeline pumping station, and bulk gasoline plant identified in paragraphs (a)(1) through (4) of this section. You are subject to the requirements in this subpart if you own or operate one or more of the affected area sources identified in paragraphs (a)(1) through (4) of this section.

(1) A bulk gasoline terminal that is not subject to the control requirements of 40 CFR part 63, subpart R (§§ 63.422, 63.423, and 63.424) or 40 CFR part 63, subpart CC (§§ 63.646, 63.648, 63.649, and 63.650).

(2) A pipeline breakout station that is not subject to the control requirements of 40 CFR part 63, subpart R (§§ 63.423 and 63.424).

(3) A pipeline pumping station.

(4) A bulk gasoline plant.

(b) If you are an owner or operator of affected sources, as defined in (a)(1) through (4) of this section, you are not required to meet the obligation to obtain a permit under 40 CFR part 70 or 40 CFR part 71 as a result of being subject to this subpart. However, you are still subject to the requirement to apply for and obtain a permit under 40 CFR part 70 or 40 CFR part 71 if you meet one or more of the applicability criteria found in 40 CFR 70.3(a) and (b) or 40 CFR part 71.3(a) and (b).

(c) Gasoline storage tanks that are located at affected sources identified in paragraphs (a)(1) through (4) of this section, and that are used only for dispensing gasoline in a manner consistent with tanks located at a gasoline dispensing facility as defined in § 63.11132, are not subject to any of the requirements in this subpart. These tanks must comply with subpart CCCCCC of this part.

(d) The loading of aviation gasoline into storage tanks at airports, and the subsequent transfer of aviation gasoline within the airport, is not subject to this subpart.

(e) The loading of gasoline into marine tank vessels at bulk facilities is not subject to this subpart.

(f) If your affected source's throughput ever exceeds an applicable throughput threshold in the definition of “bulk gasoline terminal” or in item 1 in table 2 to this subpart, the affected source will remain subject to the requirements for sources above the threshold, even if the affected source throughput later falls below the applicable throughput threshold. If your bulk gasoline plant's annual average gasoline throughput ever reaches or exceeds 4,000 gallons per day, the bulk gasoline plant will remain subject to the vapor balancing requirements, even if the affected source annual average gasoline throughput later falls below 4,000 gallons per day.

(g) For the purpose of determining gasoline throughput, as used in the definition of bulk gasoline plant and bulk gasoline terminal, the 20,000 gallons per day threshold throughput is the maximum calculated design throughout for any day, and is not an average. An enforceable State, local, or Tribal permit limitation on throughput, established prior to the applicable compliance date, may be used in lieu of the 20,000 gallons per day design capacity throughput threshold to determine whether the facility is a bulk gasoline plant or a bulk gasoline terminal.

(h) Storage tanks that are used to load gasoline into a cargo tank for the on-site redistribution of gasoline to another storage tank are subject to this subpart.

(i) For any affected source subject to the provisions of this subpart and another Federal rule, you may elect to comply only with the more stringent provisions of the applicable subparts. You must consider all provisions of the rules, including monitoring, recordkeeping, and reporting. You must identify the affected source and provisions with which you will comply in your Notification of Compliance Status required under § 63.11093. You also must demonstrate in your Notification of Compliance Status that each provision with which you will comply is at least as stringent as the otherwise applicable requirements in this subpart. You are responsible for making accurate determinations concerning the more stringent provisions; noncompliance with this rule is not excused if it is later determined that your determination was in error, and, as a result, you are violating this subpart. Compliance with this rule is your responsibility, and the Notification of Compliance Status does not alter or affect that responsibility.

(j) For new or reconstructed affected sources, as specified in § 63.11082(b) and (c), recordkeeping to document applicable throughput must begin upon startup of the affected source. For existing sources, as specified in § 63.11082(d), recordkeeping to document applicable throughput must begin on January 10, 2008. Records required under this paragraph shall be kept for a period of 5 years.

[73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4176, Jan. 24, 2011; 89 FR 39373, May 8, 2024]

§ 63.11082 - What parts of my affected source does this subpart cover?

(a) The emission sources to which this subpart applies are gasoline storage tanks, gasoline loading racks, vapor collection-equipped gasoline cargo tanks, and equipment components in vapor or liquid gasoline service that meet the criteria specified in tables 1 through 4 to this subpart.

(b) An affected source is a new affected source if you commenced construction on the affected source after November 9, 2006, and you meet the applicability criteria in § 63.11081 at the time you commenced operation.

(c) An affected source is reconstructed if you meet the criteria for reconstruction as defined in § 63.2.

(d) An affected source is an existing affected source if it is not new or reconstructed.

[73 FR 1933, Jan. 10, 2008, as amended at 89 FR 39373, May 8, 2024]

§ 63.11083 - When do I have to comply with this subpart?

(a) Except as specified in paragraphs (d) and (e) of this section, if you have a new or reconstructed affected source, you must comply with this subpart according to paragraphs (a)(1) and (2) of this section.

(1) If you start up your affected source before January 10, 2008, you must comply with the standards in this subpart no later than January 10, 2008.

(2) If you start up your affected source after January 10, 2008, you must comply with the standards in this subpart upon startup of your affected source.

(b) Except as specified in paragraphs (d) and (e) of this section, if you have an existing affected source, you must comply with the standards in this subpart no later than January 10, 2011.

(c) If you have an existing affected source that becomes subject to the control requirements in this subpart because of an increase in the daily throughput, as specified in § 63.11086(a) or in option 1 of table 2 to this subpart, you must comply with the standards in this subpart no later than 3 years after the affected source becomes subject to the control requirements in this subpart.

(d) All affected sources that commenced construction or reconstruction on or before June 10, 2022, must comply with the requirements in paragraphs (d)(1) through (5) of this section upon startup or on May 8, 2027, whichever is later. All affected sources that commenced construction or reconstruction after June 10, 2022, must comply with the requirements in paragraphs (d)(1) through (5) of this section upon startup, or on July 8, 2024, whichever is later.

(1) For bulk gasoline plants, the requirements specified in § 63.11086(a)(4) through (6).

(2) For storage vessels at bulk gasoline terminals, pipeline breakout stations, or pipeline pumping stations, the requirements specified in items 1(b), 2(c), and 2(f) in table 1 to this subpart and §§ 63.11087(g) and 63.11092(f)(1)(ii).

(3) For loading racks at bulk gasoline terminals, the requirements specified in items 1(c), 1(f), and 2(c) in table 2 to this subpart.

(4) For equipment leak inspections at bulk gasoline terminals, bulk gasoline plants, pipeline breakout stations, or pipeline pumping stations, the requirements in § 63.11089(c).

(5) For gasoline cargo tanks, the requirements specified in § 63.11092(g)(1)(ii).

(e) All affected sources that commenced construction or reconstruction on or before June 10, 2022, must comply with the requirements specified in items 2(d) and 2(e) in table 1 to this subpart upon startup or the next time the storage vessel is completely emptied and degassed, or by May 8, 2034, whichever occurs first. All affected sources that commenced construction or reconstruction after June 10, 2022, must comply with the requirements specified in items 2(d) and 2(e) in table 1 to this subpart upon startup, or on July 8, 2024, whichever is later.

[89 FR 39373, May 8, 2024]

Emission Limitations and Management Practices

§ 63.11085 - What are my general duties to minimize emissions?

Each owner or operator of an affected source under this subpart must comply with the requirements of paragraphs (a) through (c) of this section.

(a) You must, at all times, operate and maintain any affected source, including associated air pollution control equipment and monitoring equipment, in a manner consistent with safety and good air pollution control practices for minimizing emissions. The general duty to minimize emissions does not require the owner or operator to make any further efforts to reduce emissions if levels required by the applicable standard have been achieved. Determination of whether such operation and maintenance procedures are being used will be based on information available to the Administrator, which may include, but is not limited to, monitoring results, review of operation and maintenance procedures, review of operation and maintenance records, and inspection of the source.

(b) You must not allow gasoline to be handled in a manner that would result in vapor releases to the atmosphere for extended periods of time. Measures to be taken include, but are not limited to, the following:

(1) Minimize gasoline spills;

(2) Clean up spills as expeditiously as practicable;

(3) Cover all open gasoline containers and all gasoline storage tank fill-pipes with a gasketed seal when not in use; and

(4) Minimize gasoline sent to open waste collection systems that collect and transport gasoline to reclamation and recycling devices, such as oil/water separators.

(c) You must keep applicable records and submit reports as specified in §§ 63.11094(g) and 63.11095(d) or § 63.11095(e).

[89 FR 39373, May 8, 2024]

§ 63.11086 - What requirements must I meet if my facility is a bulk gasoline plant?

Each owner or operator of an affected bulk gasoline plant, as defined in § 63.11100, must comply with the requirements of paragraphs (a) through (j) of this section.

(a) Except as specified in paragraph (b) of this section, you must only load gasoline into storage tanks and cargo tanks at your facility by utilizing submerged filling, as defined in § 63.11100, and as specified in paragraph (a)(1), (2), or (3) of this section. The applicable distances in paragraphs (a)(1) and (2) of this section shall be measured from the point in the opening of the submerged fill pipe that is the greatest distance from the bottom of the storage tank. Additionally, for bulk gasoline plants with an annual average gasoline throughput of 4,000 gallons per day or more (calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365), you must only load gasoline utilizing vapor balancing as specified in paragraphs (a)(4) through (6) of this section.

(1) Submerged fill pipes installed on or before November 9, 2006, must be no more than 12 inches from the bottom of the tank.

(2) Submerged fill pipes installed after November 9, 2006, must be no more than 6 inches from the bottom of the tank.

(3) Submerged fill pipes not meeting the specifications of paragraphs (a)(1) or (a)(2) of this section are allowed if the owner or operator can demonstrate that the liquid level in the gasoline storage tank is always above the entire opening of the fill pipe. Documentation providing such demonstration must be made available for inspection by the Administrator's delegated representative during the course of a site visit.

(4) Beginning no later than the dates specified in § 63.11083, each bulk gasoline plant with an annual average gasoline throughput of 4,000 gallons per day or more shall be equipped with a vapor balance system between fixed roof gasoline storage tank(s) other than storage tank(s) vented through a closed vent system to a control device and incoming gasoline cargo tank(s) designed to capture and transfer vapors displaced during filling of fixed roof gasoline storage tank(s) other than storage tank(s) vented through a closed vent system to a control device. These lines shall be equipped with fittings that are vapor tight and that automatically and immediately close upon disconnection.

(5) Beginning no later than the dates specified in § 63.11083, each bulk gasoline plant with an annual average gasoline throughput of 4,000 gallons per day or more shall be equipped with a vapor balance system between fixed roof gasoline storage tank(s) other than storage tank(s) vented through a closed vent system to a control device and outgoing gasoline cargo tank(s) designed to capture and transfer vapors displaced during the loading of gasoline cargo tank(s). The vapor balance system shall be designed to prevent any vapors collected at one loading rack from passing to another loading rack.

(6) Beginning no later than the dates specified in § 63.11083, each owner or operator of a bulk gasoline plant subject to this subpart shall act to ensure that the following procedures are followed during all loading, unloading, and storage operations:

(i) The vapor balance system shall be connected between the cargo tank and storage tank during all gasoline transfer operations between a cargo tank and a fixed roof gasoline storage tank other than a storage tank vented through a closed vent system to a control device;

(ii) All storage tank openings, including inspection hatches and gauging and sampling devices shall be vapor tight when not in use;

(iii) No pressure relief device on a gasoline storage tank shall begin to open at a tank pressure less than 18 inches of water to minimize breathing losses;

(iv) The gasoline cargo tank compartment hatch covers shall not be opened during the gasoline transfer;

(v) All vapor balance systems shall be designed and operated at all times to prevent gauge pressure in the gasoline cargo tank from exceeding 18 inches of water and vacuum from exceeding 6 inches of water during product transfers;

(vi) No pressure vacuum relief valve in the bulk gasoline plant vapor balance system shall begin to open at a system pressure of less than 18 inches of water or at a vacuum of less than 6 inches of water; and

(vii) No gasoline shall be transferred into a cargo tank that does not have a current annual certification for vapor-tightness pursuant to the requirements in § 60.502a(e) of this chapter.

(b) Gasoline storage tanks with a capacity of less than 250 gallons are not required to comply with the control requirements in paragraph (a) of this section but must comply only with the requirements in § 63.11085(b).

(c) You must perform a leak inspection of all equipment in gasoline service and repair leaking equipment according to the requirements specified in § 63.11089.

(d) [Reserved]

(e) You must submit an Initial Notification that you are subject to this subpart by May 9, 2008, or no later than 120 days after the source becomes subject to this subpart, whichever is later unless you meet the requirements in paragraph (g) of this section. The Initial Notification must contain the information specified in paragraphs (e)(1) through (4) of this section. The notification must be submitted to the applicable U.S. Environmental Protection Agency (EPA) Regional Office and the delegated State authority, as specified in § 63.13.

(1) The name and address of the owner and the operator.

(2) The address (i.e., physical location) of the bulk gasoline plant.

(3) A statement that the notification is being submitted in response to this subpart and identifying the requirements in paragraphs (a), (b), and (c) of this section that apply to you.

(4) A brief description of the bulk gasoline plant, including the number of storage tanks in gasoline service, the capacity of each storage tank in gasoline service, and the average monthly gasoline throughput at the affected source.

(f) You must submit a Notification of Compliance Status to the applicable EPA Regional Office and the delegated State authority, as specified in § 63.13, by the compliance date specified in § 63.11083 unless you meet the requirements in paragraph (g) of this section. The Notification of Compliance Status must be signed by a responsible official who must certify its accuracy and must indicate whether the source has complied with the requirements of this subpart. If your facility is in compliance with the requirements of this subpart at the time the Initial Notification required under paragraph (e) of this section is due, the Notification of Compliance Status may be submitted in lieu of the Initial Notification provided it contains the information required under paragraph (e) of this section.

(g) If, prior to January 10, 2008, you are operating in compliance with an enforceable State, local, or tribal rule or permit that requires submerged fill as specified in § 63.11086(a), you are not required to submit an Initial Notification or a Notification of Compliance Status under paragraph (e) or paragraph (f) of this section.

(h) You must comply with the requirements of this subpart by the applicable dates specified in § 63.11083.

(i) You must keep applicable records and submit reports as specified in §§ 63.11094 and 63.11095.

[73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4177, Jan. 24, 2011; 85 FR 73919, Nov. 19, 2020; 89 FR 39373, May 8, 2024]

§ 63.11087 - What requirements must I meet for gasoline storage tanks if my facility is a bulk gasoline terminal, pipeline breakout station, or pipeline pumping station?

(a) You must meet each emission limit and management practice in Table 1 to this subpart that applies to your gasoline storage tank.

(b) You must comply with the requirements of this subpart by the applicable dates specified in § 63.11083, except that storage vessels equipped with floating roofs and not meeting the requirements of paragraph (a) of this section must be in compliance at the first degassing and cleaning activity after January 10, 2011 or by January 10, 2018, whichever is first.

(c) You must comply with the applicable testing and monitoring requirements specified in § 63.11092(f).

(d) You must submit the applicable notifications as required under § 63.11093.

(e) You must keep records and submit reports as specified in §§ 63.11094 and 63.11095.

(f) If your gasoline storage tank is subject to, and complies with, the control requirements of 40 CFR part 60, subpart Kb of this chapter, your storage tank will be deemed in compliance with this section. You must report this determination in the Notification of Compliance Status report under § 63.11093(b).

(g) No later than the dates specified in § 63.11083, if your gasoline storage tank is subject to, and complies with, the control requirements of § 60.112b(a)(2), (3), or (4) of this chapter, your storage tank will be deemed in compliance with this section. If your gasoline storage tank is subject to the control requirements of § 60.112b(a)(1) of this chapter, you must conduct lower explosive limit (LEL) monitoring as specified in § 63.11092(f)(1)(ii) to demonstrate compliance with this section. You must report this determination in the Notification of Compliance Status report under § 63.11093(b). The requirements in paragraph (f) of this section do not apply when demonstrating compliance with this paragraph (g).

[73 FR 1933, Jan. 10, 2008, as amended at 89 FR 39374, May 8, 2024]

§ 63.11088 - What requirements must I meet for gasoline loading racks if my facility is a bulk gasoline terminal?

(a) You must meet each emission limit and management practice in Table 2 to this subpart that applies to you.

(b) As an alternative for railcar cargo tanks to the requirements specified in Table 2 to this subpart, you may comply with the requirements specified in § 63.422(e).

(c) You must comply with the requirements of this subpart by the applicable dates specified in § 63.11083.

(d) You must comply with the applicable testing and monitoring requirements specified in § 63.11092. As an alternative to the pressure monitoring requirements specified in § 60.504a(d) of this chapter, you may comply with the requirements specified in § 63.11092(h).

(e) You must submit the applicable notifications as required under § 63.11093.

(f) You must keep records and submit reports as specified in §§ 63.11094 and 63.11095.

[73 FR 1933, Jan. 10, 2008, as amended at 89 FR 39374, May 8, 2024]

§ 63.11089 - What requirements must I meet for equipment leak inspections if my facility is a bulk gasoline terminal, bulk gasoline plant, pipeline breakout station, or pipeline pumping station?

(a) Each owner or operator of a bulk gasoline terminal, bulk gasoline plant, pipeline breakout station, or pipeline pumping station subject to the provisions of this subpart shall implement a leak detection and repair program for all equipment in gasoline service according to the requirements in paragraph (b) or (c) of this section, as applicable based on the compliance dates specified in § 63.11083.

(b) Perform a monthly leak inspection of all equipment in gasoline service, as defined in § 63.11100. For this inspection, detection methods incorporating sight, sound, and smell are acceptable.

(1) A logbook shall be used and shall be signed by the owner or operator at the completion of each inspection. A section of the logbook shall contain a list, summary description, or diagram(s) showing the location of all equipment in gasoline service at the facility.

(2) Each detection of a liquid or vapor leak shall be recorded in the logbook. When a leak is detected, an initial attempt at repair shall be made as soon as practicable, but no later than 5 calendar days after the leak is detected. Repair or replacement of leaking equipment shall be completed within 15 calendar days after detection of each leak, except as provided in paragraph (b)(3) of this section.

(3) Delay of repair of leaking equipment will be allowed if the repair is not feasible within 15 days. The owner or operator shall provide in the semiannual report specified in § 63.11095(c), the reason(s) why the repair was not feasible and the date each repair was completed.

(c) No later than the dates specified in § 63.11083, comply with the requirements in § 60.502a(j) of this chapter except as provided in paragraphs (c)(1) through (4) of this section. The requirements in paragraph (b) of this section do not apply when demonstrating compliance with this paragraph (c).

(1) The frequency for optical gas imaging (OGI) monitoring shall be annually rather than quarterly as specified in § 60.502a(j)(1)(i) of this chapter.

(2) The frequency for Method 21 monitoring of pumps and valves shall be annually rather than quarterly as specified in § 60.502a(j)(1)(ii)(A) and (B) of this chapter.

(3) The frequency of monitoring of pressure relief devices shall be annually and within 5 calendar days after each pressure release rather than quarterly and within 5 calendar days after each pressure release as specified in § 60.502a(j)(4)(i) of this chapter.

(4) Any pressure relief device that is located at a bulk gasoline plant or pipeline pumping station that is monitored only by non-plant personnel may be monitored after a pressure release the next time the monitoring personnel are onsite, but in no case more than 30 calendar days after a pressure release.

(d) You must comply with the requirements of this subpart by the applicable dates specified in § 63.11083.

(e) You must submit the applicable notifications as required under § 63.11093.

(f) You must keep records and submit reports as specified in §§ 63.11094 and 63.11095.

[89 FR 39375, May 8, 2024]

Testing and Monitoring Requirements

§ 63.11092 - What testing and monitoring requirements must I meet?

(a) Each owner or operator of a bulk gasoline terminal subject to the emission standard in item 1(b) of Table 2 to this subpart must comply with the requirements in paragraphs (a) through (d) of this section.

(1) Conduct a performance test on the vapor processing and collection systems according to either paragraph (a)(1)(i) or (ii) of this section, except as provided in paragraphs (a)(2) through (4) of this section.

(i) Use the test methods and procedures in § 60.503 of this chapter, except a reading of 500 parts per million shall be used to determine the level of leaks to be repaired under § 60.503(b) of this chapter.

(ii) Use alternative test methods and procedures in accordance with the alternative test method requirements in § 63.7(f).

(2) If you are operating your gasoline loading rack in compliance with an enforceable State, local, or tribal rule or permit that requires your loading rack to meet an emission limit of 80 milligrams (mg), or less, per liter of gasoline loaded (mg/l), you may submit a statement by a responsible official of your facility certifying the compliance status of your loading rack in lieu of the test required under paragraph (a)(1) of this section.

(3) If you have conducted performance testing on the vapor processing and collection systems within 5 years prior to January 10, 2008, and the test is for the affected facility and is representative of current or anticipated operating processes and conditions, you may submit the results of such testing in lieu of the test required under paragraph (a)(1) of this section, provided the testing was conducted using the test methods and procedures in § 60.503 of this chapter. Should the Administrator deem the prior test data unacceptable, the facility is still required to meet the requirement to conduct an initial performance test within 180 days of the compliance date specified in § 63.11083; thus, previous test reports should be submitted as soon as possible after January 10, 2008.

(4) The performance test requirements of § 63.11092(a) do not apply to flares defined in § 63.11100 and meeting the flare requirements in § 63.11(b). The owner or operator shall demonstrate that the flare and associated vapor collection system is in compliance with the requirements in § 63.11(b) and 40 CFR 60.503(a), (b), and (d).

(b) Each owner or operator of a bulk gasoline terminal subject to the provisions of this subpart shall install, calibrate, certify, operate, and maintain, according to the manufacturer's specifications, a continuous monitoring system (CMS) while gasoline vapors are displaced to the vapor processor systems, as specified in paragraphs (b)(1) through (5) of this section. For each facility conducting a performance test under paragraph (a)(1) of this section, and for each facility utilizing the provisions of paragraphs (a)(2) or (a)(3) of this section, the CMS must be installed by January 10, 2011.

(1) For each performance test conducted under paragraph (a)(1) of this section, the owner or operator shall determine a monitored operating parameter value for the vapor processing system using the procedures specified in paragraphs (b)(1)(i) through (iv) of this section. During the performance test, continuously record the operating parameter as specified under paragraphs (b)(1)(i) through (iv) of this section.

(i) Where a carbon adsorption system is used, the owner or operator shall monitor the operation of the system as specified in paragraphs (b)(1)(i)(A) or (B) of this section.

(A) A continuous emissions monitoring system (CEMS) capable of measuring organic compound concentration shall be installed in the exhaust air stream.

(B) As an alternative to paragraph (b)(1)(i)(A) of this section, you may choose to meet the requirements listed in paragraph (b)(1)(i)(B)(1) and (2) of this section.

(1) Carbon adsorption devices shall be monitored as specified in paragraphs (b)(1)(i)(B)(1)(i), (ii), and (iii) of this section.

(i) Vacuum level shall be monitored using a pressure transmitter installed in the vacuum pump suction line, with the measurements displayed on a gauge that can be visually observed. Each carbon bed shall be observed during one complete regeneration cycle on each day of operation of the loading rack to determine the maximum vacuum level achieved.

(ii) Conduct annual testing of the carbon activity for the carbon in each carbon bed. Carbon activity shall be tested in accordance with the butane working capacity test of the American Society for Testing and Materials (ASTM) Method D 5228-92 (incorporated by reference, see § 63.14), or by another suitable procedure as recommended by the manufacturer.

(iii) Conduct monthly measurements of the carbon bed outlet volatile organic compounds (VOC) concentration over the last 5 minutes of an adsorption cycle for each carbon bed, documenting the highest measured VOC concentration. Measurements shall be made using a portable analyzer, or a permanently mounted analyzer, in accordance with 40 CFR part 60, Appendix A-7, EPA Method 21 for open-ended lines.

(2) Develop and submit to the Administrator a monitoring and inspection plan that describes the owner or operator's approach for meeting the requirements in paragraphs (b)(1)(i)(B)(2)(i) through (v) of this section.

(i) The lowest maximum required vacuum level and duration needed to assure regeneration of the carbon beds shall be determined by an engineering analysis or from the manufacturer's recommendation and shall be documented in the monitoring and inspection plan.

(ii) The owner or operator shall verify, during each day of operation of the loading rack, the proper valve sequencing, cycle time, gasoline flow, purge air flow, and operating temperatures. Verification shall be through visual observation, or through an automated alarm or shutdown system that monitors system operation. A manual or electronic record of the start and end of a shutdown event may be used.

(iii) The owner or operator shall perform semi-annual preventive maintenance inspections of the carbon adsorption system, including the automated alarm or shutdown system for those units so equipped, according to the recommendations of the manufacturer of the system.

(iv) [Reserved]

(v) The owner or operator shall document the maximum vacuum level observed on each carbon bed from each daily inspection and the maximum VOC concentration observed from each carbon bed on each monthly inspection, as defined in the monitoring and inspection plan, and any activation of the automated alarm or shutdown system with a written entry into a logbook or other permanent form of record. Such record shall also include a description of the corrective action taken and whether such corrective actions were taken in a timely manner, as defined in the monitoring and inspection plan, as well as an estimate of the amount of gasoline loaded.

(ii) Where a refrigeration condenser system is used, a continuous parameter monitoring system (CPMS) capable of measuring temperature shall be installed immediately downstream from the outlet to the condenser section. Alternatively, a CEMS capable of measuring organic compound concentration may be installed in the exhaust air stream.

(iii) Where a thermal oxidation system is used, the owner or operator shall monitor the operation of the system as specified in paragraph (b)(1)(iii)(A) or (B) of this section.

(A) A CPMS capable of measuring temperature shall be installed in the firebox or in the ductwork immediately downstream from the firebox in a position before any substantial heat exchange occurs.

(B) As an alternative to paragraph (b)(1)(iii)(A) of this section, you may choose to meet the requirements listed in paragraphs (b)(1)(iii)(B)(1) and (2) of this section.

(1) The presence of a thermal oxidation system pilot flame shall be monitored using a heat-sensing device, such as an ultraviolet beam sensor or a thermocouple, installed in proximity of the pilot light, to indicate the presence of a flame. The heat-sensing device shall send a positive parameter value to indicate that the pilot flame is on, or a negative parameter value to indicate that the pilot flame is off.

(2) Develop and submit to the Administrator a monitoring and inspection plan that describes the owner or operator's approach for meeting the requirements in paragraphs (b)(1)(iii)(B)(2)(i) through (v) of this section.

(i) The thermal oxidation system shall be equipped to automatically prevent gasoline loading operations from beginning at any time that the pilot flame is absent.

(ii) The owner or operator shall verify, during each day of operation of the loading rack, the proper operation of the assist-air blower and the vapor line valve. Verification shall be through visual observation, or through an automated alarm or shutdown system that monitors system operation. A manual or electronic record of the start and end of a shutdown event may be used.

(iii) The owner or operator shall perform semi-annual preventive maintenance inspections of the thermal oxidation system, including the automated alarm or shutdown system for those units so equipped, according to the recommendations of the manufacturer of the system.

(iv) [Reserved]

(v) The owner or operator shall document any activation of the automated alarm or shutdown system with a written entry into a logbook or other permanent form of record. Such record shall also include a description of the corrective action taken and whether such corrective actions were taken in a timely manner, as defined in the monitoring and inspection plan, as well as an estimate of the amount of gasoline loaded.

(iv) Monitoring an alternative operating parameter or a parameter of a vapor processing system other than those listed in paragraphs (b)(1)(i) through (iii) of this section will be allowed upon demonstrating to the Administrator's satisfaction that the alternative parameter demonstrates continuous compliance with the emission standard in § 63.11088(a).

(2) Where a flare meeting the requirements in § 63.11(b) is used, a heat-sensing device, such as an ultraviolet beam sensor or a thermocouple, must be installed in proximity to the pilot light to indicate the presence of a flame.

(3) Determine an operating parameter value based on the parameter data monitored during the performance test, supplemented by engineering assessments and the manufacturer's recommendations.

(4) Provide for the Administrator's approval the rationale for the selected operating parameter value, monitoring frequency, and averaging time, including data and calculations used to develop the value and a description of why the value, monitoring frequency, and averaging time demonstrate continuous compliance with the emission standard in § 63.11088(a).

(5) If you have chosen to comply with the performance testing alternatives provided under paragraph (a)(2) or paragraph (a)(3) of this section, the monitored operating parameter value may be determined according to the provisions in paragraph (b)(5)(i) or paragraph (b)(5)(ii) of this section.

(i) Monitor an operating parameter that has been approved by the Administrator and is specified in your facility's current enforceable operating permit. At the time that the Administrator requires a new performance test, you must determine the monitored operating parameter value according to the requirements specified in paragraph (b) of this section.

(ii) Determine an operating parameter value based on engineering assessment and the manufacturer's recommendation and submit the information specified in paragraph (b)(4) of this section for approval by the Administrator. At the time that the Administrator requires a new performance test, you must determine the monitored operating parameter value according to the requirements specified in paragraph (b) of this section.

(c) For performance tests performed after the initial test required under paragraph (a) of this section, the owner or operator shall document the reasons for any change in the operating parameter value since the previous performance test.

(d) Each owner or operator of a bulk gasoline terminal subject to the provisions of this subpart shall comply with the requirements in paragraphs (d)(1) through (3) of this section.

(1) Operate the vapor processing system in a manner not to exceed or not to go below, as appropriate, the operating parameter value for the parameters described in paragraph (b)(1) of this section.

(2) In cases where an alternative parameter pursuant to paragraph (b)(1)(iv) or (b)(5)(i) of this section is approved, each owner or operator shall operate the vapor processing system in a manner not to exceed or not to go below, as appropriate, the alternative operating parameter value.

(3) Operation of the vapor processing system in a manner exceeding or going below the operating parameter value, as appropriate, shall constitute a violation of the emission standard in § 63.11088(a).

(e) Each owner or operator of a bulk gasoline terminal subject to the emission standard in item 1(c) of table 2 to this subpart for loading racks must comply with the requirements in paragraphs (e)(1) through (4) of this section, as applicable.

(1) For each bulk gasoline terminal complying with the emission limitations in item 1 of table 3 to this subpart (thermal oxidation system), conduct a performance test no later than 180 days after becoming subject to the applicable emission limitation in table 3 and conduct subsequent performance tests at least once every 60 calendar months following the methods specified in § 60.503a(a) and (c) of this chapter. Prior to conducting this performance test, you must continue to meet the monitoring and operating limits that apply based on the previously conducted performance test. A previously conducted performance test may be used to satisfy this requirement if the conditions in paragraphs (e)(1)(i) through (v) of this section are met.

(i) The performance test was conducted on or after May 8, 2022.

(ii) No changes have been made to the process or control device since the time of the performance test.

(iii) The operating conditions, test methods, and test requirements (e.g., length of test) used for the previous performance test conform to the requirements in paragraph (e)(1) of this section.

(iv) The temperature in the combustion zone was recorded during the performance test as specified in § 60.503a(c)(8)(i) of this chapter and can be used to establish the operating limit as specified in § 60.503a(c)(8)(ii) through (iv) of this chapter.

(v) The performance test demonstrates compliance with the emission limit specified in item 1(a) in table 3 to this subpart.

(2) For each bulk gasoline terminal complying with the emission limitations in item 1 of table 3 to this subpart (thermal oxidation system), comply with either the provisions in paragraph (e)(2)(i) or (ii) of this section.

(i) Install, operate, and maintain a CPMS to measure the combustion zone temperature according to § 60.504a(a) of this chapter and maintain the 3-hour rolling average combustion zone temperature when gasoline cargo tanks are being loaded at or above the operating limit set during the most recent performance test following the procedures specified in § 60.503a(c)(8) of this chapter. Valid operating data must exclude periods when there is no liquid product being loaded. If previous contents of the cargo tanks are known, you may also exclude periods when liquid product is loaded but no gasoline cargo tanks are being loaded provided that you excluded these periods in the determination of the combustion zone temperature operating limit according to the provisions in § 60.503a(c)(8)(ii) of this chapter.

(ii) Operate each thermal oxidation system in compliance with the requirements for a flare in § 60.502a(c)(3) of this chapter and the monitoring requirements in § 60.504a(c) of this chapter.

(3) For each bulk gasoline terminal complying with the emission limitations in item 2 of table 3 to this subpart (flare), install, operate, and maintain flare continuous parameter monitoring systems as specified in in § 60.504a(c) of this chapter.

(4) For each bulk gasoline terminal complying with the emission limitation in item 3 of table 3 to this subpart (carbon adsorption system, refrigerated condenser, or other vapor recovery system), install, operate, and maintain a continuous emission monitoring system (CEMS) to measure the total organic compounds (TOC) concentration according to § 60.504a(b) of this chapter and conduct performance evaluations as specified in § 60.503a(a) and (d) of this chapter. For periods of CEMS outages, you may use the limited alternative monitoring methods as specified in § 60.504a(e) of this chapter.

(f) Each owner or operator subject to the emission standard in § 63.11087 for gasoline storage tanks shall comply with the requirements in paragraphs (f)(1) through (3) of this section.

(1) If your gasoline storage tank is equipped with an internal floating roof,

(i) You must perform inspections of the floating roof system according to the requirements of § 60.113b(a) of this chapter if you are complying with option 2(b) in table 1 to this subpart, or according to the requirements of § 63.1063(c)(1) if you are complying with option 2(e) in table 1 to this subpart.

(ii) No later than the dates specified in § 63.11083, you must conduct LEL monitoring according to the provisions in § 63.425(j). A deviation of the LEL level is considered an inspection failure under § 60.113b(a)(2) of this chapter or § 63.1063(d)(2) and must be remedied as such. Any repairs must be confirmed effective through re-monitoring of the LEL and meeting the levels in options 2(c) and 2(f) in table 1 to this subpart within the timeframes specified in § 60.113b(a)(2) or § 63.1063(e), as applicable.

(2) If your gasoline storage tank is equipped with an external floating roof, you must perform inspections of the floating roof system according to the requirements of § 60.113b(b) of this chapter if you are complying with option 2(d) in table 1 to this subpart, or according to the requirements of § 63.1063(c)(2) if you are complying with option 2(e) in table 1 to this subpart.

(3) If your gasoline storage tank is equipped with a closed vent system and control device, you must conduct a performance test and determine a monitored operating parameter value in accordance with the requirements in paragraphs (a) through (d) of this section, except that the applicable level of control specified in paragraph (a)(2) of this section shall be a 95-percent reduction in inlet TOC levels rather than 80 mg/l of gasoline loaded.

(g) The annual certification test for gasoline cargo tanks shall consist of the test methods specified in paragraph (g)(1) or (2) of this section. Affected facilities that are subject to subpart XX to part 60 of this chapter may elect, after notification to the subpart XX delegated authority, to comply with paragraphs (g)(1) and (2) of this section.

(1) EPA Method 27 of appendix A-8 to part 60 of this chapter. Conduct the test using a time period (t) for the pressure and vacuum tests of 5 minutes. The initial pressure (Pi) for the pressure test shall be 460 millimeters (mm) of water (18 inches of water), gauge. The initial vacuum (Vi) for the vacuum test shall be 150 mm of water (6 inches of water), gauge.

(i) The maximum allowable pressure and vacuum changes (Δ p, Δ v) for all affected gasoline cargo tanks is 3 inches of water, or less, in 5 minutes.

(ii) No later than the dates specified in § 63.11083, the maximum allowable pressure and vacuum changes (Δ p, Δ v) for all affected gasoline cargo tanks is provided in column 3 of table 2 in § 63.425(e). The requirements in paragraph (g)(1)(i) of this section do not apply when demonstrating compliance with this paragraph (g)(1)(ii).

(2) Railcar bubble leak test procedures. As an alternative to the annual certification test required under paragraph (g)(1) of this section for certification leakage testing of gasoline cargo tanks, the owner or operator may comply with paragraphs (g)(2)(i) and (ii) of this section for railcar cargo tanks, provided the railcar cargo tank meets the requirement in paragraph (g)(2)(iii) of this section.

(i) Comply with the requirements of 49 CFR 173.31(d), 179.7, 180.509, and 180.511 for the periodic testing of railcar cargo tanks.

(ii) The leakage pressure test procedure required under 49 CFR 180.509(j) and used to show no indication of leakage under 49 CFR 180.511(f) shall be a bubble leak test procedure meeting the requirements in 49 CFR 179.7, 180.505, and 180.509. Use of ASTM E515-95 (Reapproved 2000) or BS EN 1593:1999 (incorporated by reference, see § 63.14) complies with those requirements.

(iii) The alternative requirements in this paragraph (g)(2) may not be used for any railcar cargo tank that collects gasoline vapors from a vapor balance system and the system complies with a Federal, State, local, or Tribal rule or permit. A vapor balance system is a piping and collection system designed to collect gasoline vapors displaced from a storage vessel, barge, or other container being loaded, and routes the displaced gasoline vapors into the railcar cargo tank from which liquid gasoline is being unloaded.

(h) As an alternative to the pressure monitoring requirements in § 60.504a(d) of this chapter, you may comply with the pressure monitoring requirements in § 60.503(d) of this chapter during any performance test or performance evaluation conducted under § 63.11092(e) to demonstrate compliance with the provisions in § 60.502a(h) of this chapter.

(i) Performance tests conducted for this subpart shall be conducted under such conditions as the Administrator specifies to the owner or operator, based on representative performance (i.e., performance based on normal operating conditions) of the affected source. Performance tests shall be conducted under representative conditions when liquid product is being loaded into gasoline cargo tanks and shall include periods between gasoline cargo tank loading (when one cargo tank is disconnected and another cargo tank is moved into position for loading) provided that liquid product loading into gasoline cargo tanks is conducted for at least a portion of each 5 minute block of the performance test. You may not conduct performance tests during periods of malfunction. You must record the process information that is necessary to document operating conditions during the test and include in such record an explanation to support that such conditions represent normal operation. Upon request, the owner or operator shall make available to the Administrator such records as may be necessary to determine the conditions of performance tests.

[73 FR 1933, Jan. 10, 2008, as amended at 73 FR 12276, Mar. 7, 2008; 76 FR 4177, Jan. 24, 2011; 89 FR 39375, May 8, 2024]

Notifications, Records, and Reports

§ 63.11093 - What notifications must I submit and when?

(a) Each owner or operator of an affected source under this subpart must submit an Initial Notification as specified in § 63.9(b). If your facility is in compliance with the requirements of this subpart at the time the Initial Notification is due, the Notification of Compliance Status required under paragraph (b) of this section may be submitted in lieu of the Initial Notification.

(b) Each owner or operator of an affected source under this subpart must submit a Notification of Compliance Status as specified in § 63.9(h). The Notification of Compliance Status must specify which of the compliance options included in Table 1 to this subpart is used to comply with this subpart.

(c) Each owner or operator of an affected bulk gasoline terminal under this subpart must submit a Notification of Performance Test or Performance Evaluation, as specified in subpart A to this part, prior to initiating testing required by this subpart.

(d) Each owner or operator of any affected source under this subpart must submit additional notifications specified in § 63.9, as applicable.

(e) The owner or operator must submit all Notification of Compliance Status reports in PDF format to the EPA following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Gasoline Distribution Sector Lead.

[73 FR 1933, Jan. 10, 2008, as amended at 89 FR 39377, May 8, 2024]

§ 63.11094 - What are my recordkeeping requirements?

(a) Each owner or operator of a bulk gasoline terminal or pipeline breakout station whose storage vessels are subject to the provisions of this subpart shall keep records as specified in paragraphs (a)(1) and (2) of this section.

(1) If you are complying with options 2(a), 2(b), or 2(d) in table 1 to this subpart, keep records as specified in § 60.115b of this chapter except records shall be kept for at least 5 years. If you are complying with the requirements of option 2(e) in table 1 to this subpart, you shall keep records as specified in § 63.1065.

(2) If you are complying with options 2(c) or 2(f) in table 1 to this subpart, keep records of each LEL monitoring event as specified in paragraphs (a)(2)(i) through (ix) of this section for at least 5 years.

(i) Date and time of the LEL monitoring, and the storage vessel being monitored.

(ii) A description of the monitoring event (e.g., monitoring conducted concurrent with visual inspection required under § 60.113b(a)(2) of this chapter or § 63.1063(d)(2); monitoring that occurred on a date other than the visual inspection required under § 60.113b(a)(2) or § 63.1063(d)(2); re-monitoring due to high winds; re-monitoring after repair attempt).

(iii) Wind speed at the top of the storage vessel on the date of LEL monitoring.

(iv) The LEL meter manufacturer and model number used, as well as an indication of whether tubing was used during the LEL monitoring, and if so, the type and length of tubing used.

(v) Calibration checks conducted before and after making the measurements, including both the span check and instrumental offset. This includes the hydrocarbon used as the calibration gas, the Certificate of Analysis for the calibration gas(es), the results of the calibration check, and any corrective action for calibration checks that do not meet the required response.

(vi) Location of the measurements and the location of the floating roof.

(vii) Each measurement (taken at least once every 15 seconds). The records should indicate whether the recorded values were automatically corrected using the meter's programming. If the values were not automatically corrected, record both the raw (as the calibration gas) and corrected measurements, as well as the correction factor used.

(viii) Each 5-minute rolling average reading.

(ix) If the vapor concentration of the storage vessel was above 25 percent of the LEL on a 5-minue rolling average basis, a description of whether the floating roof was repaired, replaced, or taken out of gasoline service.

(b) Each owner or operator of a bulk gasoline terminal subject to the provisions in items 1(e), 1(f), or 2(c) in table 2 to this subpart or bulk gasoline plant subject to the requirements in § 63.11086(a)(6) shall keep records in either a hardcopy or electronic form of the test results for each gasoline cargo tank loading at the facility as specified in paragraphs (b)(1) through (3) of this section for at least 5 years.

(1) Annual certification testing performed under § 63.11092(g)(1) and periodic railcar bubble leak testing performed under § 63.11092(g)(2).

(2) The documentation file shall be kept up to date for each gasoline cargo tank loading at the facility. The documentation for each test shall include, as a minimum, the following information:

(i) Name of test: Annual Certification Test—Method 27 or Periodic Railcar Bubble Leak Test Procedure.

(ii) Cargo tank owner's name and address.

(iii) Cargo tank identification number.

(iv) Test location and date.

(v) Tester name and signature.

(vi) Witnessing inspector, if any: Name, signature, and affiliation.

(vii) Vapor tightness repair: Nature of repair work and when performed in relation to vapor tightness testing.

(viii) Test results: Tank or compartment capacity; test pressure; pressure or vacuum change, mm of water; time period of test; number of leaks found with instrument; and leak definition.

(3) If you are complying with the alternative requirements in § 63.11088(b), you must keep records documenting that you have verified the vapor tightness testing according to the requirements of the Administrator.

(c) Each owner or operator subject to the equipment leak provisions of § 63.11089 shall prepare and maintain a record describing the types, identification numbers, and locations of all equipment in gasoline service. For facilities electing to implement an instrument program under § 63.11089(b), the record shall contain a full description of the program.

(d) Each owner or operator of an affected source subject to equipment leak inspections under § 63.11089(b) shall record in the logbook for each leak that is detected the information specified in paragraphs (d)(1) through (7) of this section.

(1) The equipment type and identification number.

(2) The nature of the leak (i.e., vapor or liquid) and the method of detection (i.e., sight, sound, or smell).

(3) The date the leak was detected and the date of each attempt to repair the leak.

(4) Repair methods applied in each attempt to repair the leak.

(5) “Repair delayed” and the reason for the delay if the leak is not repaired within 15 calendar days after discovery of the leak.

(6) The expected date of successful repair of the leak if the leak is not repaired within 15 days.

(7) The date of successful repair of the leak.

(e) Each owner or operator of an affected source subject to § 63.11089(c) or § 60.503a(a)(2) of this chapter shall maintain records of each leak inspection and leak identified under § 63.11089(c) or § 60.503a(a)(2) as specified in paragraphs (e)(1) through (5) of this section for at least 5 years.

(1) An indication if the leak inspection was conducted under § 63.11089(c) or § 60.503a(a)(2) of this chapter.

(2) Leak determination method used for the leak inspection.

(3) For leak inspections conducted with Method 21 of appendix A-7 to part 60 of this chapter, keep the following additional records:

(i) Date of inspection.

(ii) Inspector name.

(iii) Monitoring instrument identification.

(iv) Identification of all equipment surveyed and the instrument reading for each piece of equipment.

(v) Date and time of instrument calibration and initials of operator performing the calibration.

(vi) Calibration gas cylinder identification, certification date, and certified concentration.

(vii) Instrument scale used.

(viii) Results of the daily calibration drift assessment.

(4) For leak inspections conducted with OGI, keep the records specified in section 12 of appendix K to part 60 of this chapter.

(5) For each leak detected during a leak inspection or by audio/visual/olfactory methods during normal duties, record the following information:

(i) The equipment type and identification number.

(ii) The date the leak was detected, the name of the person who found the leak, the nature of the leak (i.e., vapor or liquid), and the method of detection (i.e., audio/visual/olfactory, Method 21, or OGI).

(iii) The date of each attempt to repair the leak and the repair methods applied in each attempt to repair the leak.

(iv) The date of successful repair of the leak, the method of monitoring used to confirm the repair, and if Method 21 of appendix A-7 to part 60 of this chapter is used to confirm the repair, the maximum instrument reading measured by Method 21 of appendix A-7. If OGI is used to confirm the repair, keep video footage of the repair confirmation.

(v) For each repair delayed beyond 15 calendar days after discovery of the leak, record “Repair delayed”, the reason for the delay, and the expected date of successful repair. The owner or operator (or designate) whose decision it was that repair could not be carried out in the 15- calendar day timeframe must sign the record.

(vi) For each leak that is not repairable, the maximum instrument reading measured by Method 21 of appendix A-7 to part 60 of this chapter at the time the leak is determined to be not repairable, a video captured by the OGI camera showing that emissions are still visible, or a signed record that the leak is still detectable via audio/visual/olfactory methods.

(f) Each owner or operator of a bulk gasoline terminal subject to the loading rack provisions of item 1(c) of table 2 to this subpart or storage vessel provisions in § 63.11092(f) shall:

(1) Keep an up-to-date, readily accessible record of the continuous monitoring data required under § 63.11092(b) or (f). This record shall indicate the time intervals during which loadings of gasoline cargo tanks have occurred or, alternatively, shall record the operating parameter data only during such loadings. The date and time of day shall also be indicated at reasonable intervals on this record.

(2) Record and report simultaneously with the Notification of Compliance Status required under § 63.11093(b):

(i) All data and calculations, engineering assessments, and manufacturer's recommendations used in determining the operating parameter value under § 63.11092(b) or (f); and

(ii) The following information when using a flare under provisions of § 63.11(b) to comply with § 63.11087(a):

(A) Flare design (i.e., steam-assisted, air-assisted, or non-assisted); and

(B) All visible emissions (VE) readings, heat content determinations, flow rate measurements, and exit velocity determinations made during the compliance determination required under § 63.11092(e)(3).

(3) Keep an up-to-date, readily accessible copy of the monitoring and inspection plan required under § 63.11092(b)(1)(i)(B)(2) or (b)(1)(iii)(B)(2).

(4) Keep an up-to-date, readily accessible record as specified in § 63.11092(b)(1)(i)(B)(2)(v) or (b)(1)(iii)(B)(2)(v).

(5) If an owner or operator requests approval to use a vapor processing system or monitor an operating parameter other than those specified in § 63.11092(b), the owner or operator shall submit a description of planned reporting and recordkeeping procedures.

(g) Each owner or operator of a bulk gasoline terminal subject to the loading rack provisions of item 1(c) of table 2 to this subpart shall keep records specified in paragraphs (g)(1) through (3) of this section, as applicable, for at least 5 years unless otherwise specified.

(1) For each thermal oxidation system used to comply with the provisions in § 63.11092(e)(2)(i) by monitoring the combustion zone temperature, for each pressure CPMS used to comply with the requirements in § 60.502a(h) of this chapter, and for each vapor recovery system used to comply with the provisions in item 3 of table 3 to this subpart, maintain records, as applicable, of:

(i) The applicable operating or emission limit for the CMS. For combustion zone temperature operating limits, include the applicable date range the limit applies based on when the performance test was conducted.

(ii) Each 3-hour rolling average combustion zone temperature measured by the temperature CPMS, each 5-minute average reading from the pressure CPMS, and each 3-hour rolling average TOC concentration (as propane) measured by the TOC CEMS.

(iii) For each deviation of the 3-hour rolling average combustion zone temperature operating limit, maximum loading pressure specified in § 60.502a(h) of this chapter, or 3-hour rolling average TOC concentration (as propane), the start date and time, duration, cause, and the corrective action taken.

(iv) For each period when there was a CMS outage or the CMS was out of control, the start date and time, duration, cause, and the corrective action taken. For TOC CEMS outages where the limited alternative for vapor recovery systems in § 60.504a(e) of this chapter is used, the corrective action taken shall include an indication of the use of the limited alternative for vapor recovery systems in § 60.504a(e).

(v) Each inspection or calibration of the CMS including a unique identifier, make, and model number of the CMS, and date of calibration check. For TOC CEMS, include the type of CEMS used (i.e., flame ionization detector, nondispersive infrared analyzer) and an indication of whether methane is excluded from the TOC concentration reported in paragraph (g)(1)(ii) of this section.

(vi) TOC CEMS outages where the limited alternative for vapor recovery systems in § 60.504a(e) of this chapter is used, also keep records of:

(A) The quantity of liquid product loaded in gasoline cargo tanks for the past 10 adsorption cycles prior to the CEMS outage.

(B) The vacuum pressure, purge gas quantities, and duration of the vacuum/purge cycles used for the past 10 desorption cycles prior to the CEMS outage.

(C) The quantity of liquid product loaded in gasoline cargo tanks for each adsorption cycle while using the alternative.

(D) The vacuum pressure, purge gas quantities, and duration of the vacuum/purge cycles for each desorption cycle while using the alternative.

(2) For each thermal oxidation system used to comply with the provision in § 63.11092(e)(2)(ii) and for each flare used to comply with the provision in item 2 of table 3 to this subpart, maintain records of:

(i) The output of the monitoring device used to detect the presence of a pilot flame as required in § 63.670(b) for a minimum of 2 years. Retain records of each 15-minute block during which there was at least one minute that no pilot flame is present when gasoline vapors were routed to the flare for a minimum of 5 years. The record must identify the start and end time and date of each 15-minute block.

(ii) Visible emissions observations as specified in paragraphs (g)(2)(ii)(A) and (B) of this section, as applicable, for a minimum of 3 years.

(A) If visible emissions observations are performed using Method 22 of appendix A-7 to part 60 of this chapter, the record must identify the date, the start and end time of the visible emissions observation, and the number of minutes for which visible emissions were observed during the observation. If the owner or operator performs visible emissions observations more than one time during a day, include separate records for each visible emissions observation performed.

(B) For each 2-hour period for which visible emissions are observed for more than 5 minutes in 2 consecutive hours but visible emissions observations according to Method 22 of appendix A-7 to part 60 of this chapter were not conducted for the full 2-hour period, the record must include the date, the start and end time of the visible emissions observation, and an estimate of the cumulative number of minutes in the 2-hour period for which emissions were visible based on best information available to the owner or operator.

(iii) Each 15-minute block period during which operating values are outside of the applicable operating limits specified in § 63.670(d) through (f) when liquid product is being loaded into gasoline cargo tanks for at least 15-minutes identifying the specific operating limit that was not met.

(iv) The 15-minute block average cumulative flows for the thermal oxidation system vent gas or flare vent gas and, if applicable, total steam, perimeter assist air, and premix assist air specified to be monitored under § 63.670(i), along with the date and start and end time for the 15-minute block. If multiple monitoring locations are used to determine cumulative vent gas flow, total steam, perimeter assist air, and premix assist air, retain records of the 15-minute block average flows for each monitoring location for a minimum of 2 years, and retain the 15-minute block average cumulative flows that are used in subsequent calculations for a minimum of 5 years. If pressure and temperature monitoring is used, retain records of the 15-minute block average temperature, pressure and molecular weight of the thermal oxidation system vent gas, flare vent gas, or assist gas stream for each measurement location used to determine the 15-minute block average cumulative flows for a minimum of 2 years, and retain the 15-minute block average cumulative flows that are used in subsequent calculations for a minimum of 5 years. If you use the supplemental gas flow rate monitoring alternative in § 60.502a(c)(3)(viii) of this chapter, the required supplemental gas flow rate (winter and summer, if applicable) and the actual monitored supplemental gas flow rate for the 15-minute block. Retain the supplemental gas flow rate records for a minimum of 5 years.

(v) The thermal oxidation system vent gas or flare vent gas compositions specified to be monitored under § 63.670(j). Retain records of individual component concentrations from each compositional analyses for a minimum of 2 years. If NHVvg analyzer is used, retain records of the 15-minute block average values for a minimum of 5 years. If you demonstrate your gas streams have consistent composition using the provisions in § 63.670(j)(6) as specified in § 60.502a(c)(3)(vii) of this chapter, retain records of the required minimum ratio of gasoline loaded to total liquid product loaded and the actual ratio on a 15-minute block basis. If applicable, you must retain records of the required minimum gasoline loading rate as specified in § 60.502a(c)(3)(vii) and the actual gasoline loading rate on a 15-minute block basis for a minimum of 5 years.

(vi) Each 15-minute block average operating parameter calculated following the methods specified in § 63.670(k) through (n), as applicable.

(vii) All periods during which the owner or operator does not perform monitoring according to the procedures in § 63.670(g), (i), and (j) or in § 60.502a(c)(3)(vii) and (viii) of this chapter as applicable. Note the start date, start time, and duration in minutes for each period.

(viii) An indication of whether “vapors displaced from gasoline cargo tanks during product loading” excludes periods when liquid product is loaded but no gasoline cargo tanks are being loaded or if liquid product loading is assumed to be loaded into gasoline cargo tanks according to the provisions in § 60.502a(c)(3)(i) of this chapter, records of all time periods when “vapors displaced from gasoline cargo tanks during product loading”, and records of time periods when there were no “vapors displaced from gasoline cargo tanks during product loading”.

(ix) If you comply with the flare tip velocity operating limit using the one-time flare tip velocity operating limit compliance assessment as provided in § 60.502a(c)(3)(ix) of this chapter, maintain records of the applicable one-time flare tip velocity operating limit compliance assessment for as long as you use this compliance method.

(x) For each parameter monitored using a CMS, retain the records specified in paragraphs (g)(2)(x)(A) through (C) of this section, as applicable:

(A) For each deviation, record the start date and time, duration, cause, and corrective action taken.

(B) For each period when there is a CMS outage or the CMS is out of control, record the start date and time, duration, cause, and corrective action taken.

(C) Each inspection or calibration of the CMS including a unique identifier, make, and model number of the CMS, and date of calibration check.

(3) Records of all 5-minute time periods during which liquid product is loaded into gasoline cargo tanks or assumed to be loaded into gasoline cargo tanks and records of all 5-minute time periods when there was no liquid product loaded into gasoline cargo tanks.

(h) Each owner or operator of a bulk gasoline terminal subject to the provisions in items 1(e), 1(f), or 2(c) in table 2 to this subpart or bulk gasoline plant subject to the requirements in § 63.11086(a)(6) shall maintain records of each instance in which liquid product was loaded into a gasoline cargo tank for which vapor tightness documentation required under § 60.502(e)(1) or § 60.502a(e)(1) of this chapter, as applicable, was not provided or available in the terminal's or plant's records for at least 5 years. These records shall include, at a minimum:

(1) Cargo tank owner and address.

(2) Cargo tank identification number.

(3) Date and time liquid product was loaded into a gasoline cargo tank without proper documentation.

(4) Date proper documentation was received or statement that proper documentation was never received.

(i) Each owner or operator of a bulk gasoline terminal or bulk gasoline plant subject to the provisions of this subpart shall maintain records for at least 5 years of each instance when liquid product was loaded into gasoline cargo tanks not using submerged filling, or, if applicable, not equipped with vapor collection or balancing equipment that is compatible with the terminal's vapor collection system or plant's vapor balancing system. These records shall include, at a minimum:

(1) Date and time of liquid product loading into gasoline cargo tank not using submerged filling, improperly equipped, or improperly connected.

(2) Type of deviation (e.g., not submerged filling, incompatible equipment, not properly connected).

(3) Cargo tank identification number.

(j) Each owner or operator of a bulk gasoline plant subject to the requirements in § 63.11086(a)(6) shall maintain records for at least 5 years of instances when gasoline was loaded between gasoline cargo tanks and storage tanks and the plant's vapor balancing system was not properly connected between the gasoline cargo tank and storage tank. These records shall include, at a minimum:

(1) Date and time of gasoline loading between a gasoline cargo tank and a storage tank that was not properly connected.

(2) Cargo tank identification number and storage tank identification number.

(k) Each owner or operator of an affected source under this subpart shall keep the following records for each deviation of an emissions limitation (including operating limit), work practice standard, or operation and maintenance requirement in this subpart.

(1) Date, start time, and duration of each deviation.

(2) List of the affected sources or equipment for each deviation, an estimate of the quantity of each regulated pollutant emitted over any emission limit and a description of the method used to estimate the emissions.

(3) Actions taken to minimize emissions in accordance with § 63.11085(a).

(l) Each owner or operator of a bulk gasoline terminal or bulk gasoline plant subject to the provisions of this subpart shall maintain records of the average gasoline throughput (in gallons per day) for at least 5 years.

(m) Keep written procedures required under § 63.8(d)(2) on record for the life of the affected source or until the affected source is no longer subject to the provisions of this part, to be made available for inspection, upon request, by the Administrator. If the performance evaluation plan is revised, you shall keep previous (i.e., superseded) versions of the performance evaluation plan on record to be made available for inspection, upon request, by the Administrator, for a period of 5 years after each revision to the plan. The program of corrective action shall be included in the plan as required under § 63.8(d)(2).

(n) Keep records of each performance test or performance evaluation conducted and each notification and report submitted to the Administrator for at least 5 years. For each performance test, include an indication of whether liquid product loading is assumed to be loaded into a gasoline cargo tank or periods when liquid product is loaded but no gasoline cargo tanks are being loaded are excluded in the determination of the combustion zone temperature operating limit according to the provision in § 60.503a(c)(8)(ii) of this chapter. If complying with the alternative in § 63.11092(h), for each performance test or performance evaluation conducted, include the pressure every 5 minutes while a gasoline cargo tank is being loaded and the highest instantaneous pressure that occurs during each loading.

(o) Any records required to be maintained by this subpart that are submitted electronically via the EPA's Compliance and Emissions Reporting Interface (CEDRI) may be maintained in electronic format. This ability to maintain electronic copies does not affect the requirement for facilities to make records, data, and reports available upon request to a delegated authority or the EPA as part of an on-site compliance evaluation.

[89 FR 39377, May 7, 2024]

§ 63.11095 - What are my reporting requirements?

(a) Reporting requirements for performance tests. Prior to November 4, 2024, each owner or operator of an affected source under this subpart shall submit performance test reports to the Administrator according to the requirements in § 63.13. Beginning on November 4, 2024, within 60 days after the date of completing each performance test required by this subpart, you must submit the results of the performance test following the procedures specified in § 63.9(k). As required by § 63.7(g)(2)(iv), you must include the value for the combustion zone temperature operating parameter limit set based on your performance test in the performance test report. If the monitoring alternative in § 63.11092(h) is used, indicate that this monitoring alternative is being used, identify each loading rack that loads gasoline cargo tanks at the bulk gasoline terminal subject to the provisions of this subpart, and report the highest instantaneous pressure monitored during the performance test or performance evaluation for each identified loading rack. Data collected using test methods supported by the EPA's Electronic Reporting Tool (ERT) as listed on the EPA's ERT website (https://www.epa.gov/electronic-reporting-air-emissions/electronic-reporting-tool-ert) at the time of the test must be submitted in a file format generated using the EPA's ERT. Alternatively, you may submit an electronic file consistent with the extensible markup language (XML) schema listed on the EPA's ERT website. Data collected using test methods that are not supported by the EPA's ERT as listed on the EPA's ERT website at the time of the test must be included as an attachment in the ERT or an alternate electronic file.

(b) Reporting requirements for performance evaluations. Prior to November 4, 2024, each owner or operator of an affected source under this subpart shall submit performance evaluations to the Administrator according to the requirements in § 63.13. Beginning on November 4, 2024, within 60 days after the date of completing each CEMS performance evaluation, you must submit the results of the performance evaluation following the procedures specified in § 63.9(k). If the monitoring alternative in § 63.11092(h) is used, indicate that this monitoring alternative is being used, identify each loading rack that loads gasoline cargo tanks at the bulk gasoline terminal subject to the provisions of this subpart, and report the highest instantaneous pressure monitored during the performance test or performance evaluation for each identified loading rack. The results of performance evaluations of CEMS measuring relative accuracy test audit (RATA) pollutants that are supported by the EPA's ERT as listed on the EPA's ERT website at the time of the evaluation must be submitted in a file format generated using the EPA's ERT. Alternatively, you may submit an electronic file consistent with the XML schema listed on the EPA's ERT website. The results of performance evaluations of CEMS measuring RATA pollutants that are not supported by the EPA's ERT as listed on the EPA's ERT website at the time of the evaluation must be included as an attachment in the ERT or an alternate electronic file.

(c) Reporting requirements prior to May 8, 2027. Prior to May 8, 2027, each owner or operator of a source subject to the requirements of this subpart shall submit reports as specified in paragraphs (c)(1) through (3) of this section, as applicable.

(1) Each owner or operator of a bulk terminal or a pipeline breakout station subject to the control requirements of this subpart shall include in a semiannual compliance report to the Administrator the following information, as applicable:

(i) For storage vessels, if you are complying with options 2(a), 2(b), or 2(d) in table 1 to this subpart, the information specified in § 60.115b(a), (b), or (c) of this chapter, depending upon the control equipment installed, or, if you are complying with option 2(e) in table 1 to this subpart, the information specified in § 63.1066.

(ii) For loading racks, each loading of a gasoline cargo tank for which vapor tightness documentation had not been previously obtained by the facility.

(iii) For equipment leak inspections, the number of equipment leaks not repaired within 15 days after detection.

(iv) For storage vessels complying with § 63.11087(b) after January 10, 2011, the storage vessel's Notice of Compliance Status information can be included in the next semi-annual compliance report in lieu of filing a separate Notification of Compliance Status report under § 63.11093.

(2) Each owner or operator of an affected source subject to the control requirements of this subpart shall submit an excess emissions report to the Administrator at the time the semiannual compliance report is submitted. Excess emissions events under this subpart, and the information to be included in the excess emissions report, are specified in paragraphs (c)(2)(i) through (v) of this section.

(i) Each instance of a non-vapor-tight gasoline cargo tank loading at the facility in which the owner or operator failed to take steps to assure that such cargo tank would not be reloaded at the facility before vapor tightness documentation for that cargo tank was obtained.

(ii) Each reloading of a non-vapor-tight gasoline cargo tank at the facility before vapor tightness documentation for that cargo tank is obtained by the facility in accordance with § 63.11094(b).

(iii) Each exceedance or failure to maintain, as appropriate, the monitored operating parameter value determined under § 63.11092(b). The report shall include the monitoring data for the days on which exceedances or failures to maintain have occurred, and a description and timing of the steps taken to repair or perform maintenance on the vapor collection and processing systems or the CMS.

(iv) [Reserved]

(v) For each occurrence of an equipment leak for which no repair attempt was made within 5 days or for which repair was not completed within 15 days after detection:

(A) The date on which the leak was detected;

(B) The date of each attempt to repair the leak;

(C) The reasons for the delay of repair; and

(D) The date of successful repair.

(3) Each owner or operator of a bulk gasoline plant or a pipeline pumping station shall submit a semiannual excess emissions report, including the information specified in paragraphs (c)(1)(iii) and (c)(2)(v) of this section, only for a 6-month period during which an excess emission event has occurred. If no excess emission events have occurred during the previous 6-month period, no report is required.

(d) Reporting requirements for semiannual reports on or after May 8, 2027. On or after May 8, 2027, you must submit to the Administrator semiannual reports with the applicable information in paragraphs (d)(1) through (9) of this section following the procedure specified in paragraph (e) of this section.

(1) Report the following general facility information:

(i) Facility name.

(ii) Facility physical address, including city, county, and State.

(iii) Latitude and longitude of facility's physical location. Coordinates must be in decimal degrees with at least five decimal places.

(iv) The following information for the contact person:

(A) Name.

(B) Mailing address.

(C) Telephone number.

(D) Email address.

(v) The type of facility (bulk gasoline plant with an annual average gasoline throughput less than 4,000 gallons per day; bulk gasoline plant with an annual average gasoline throughput of 4,000 gallons per day or more; bulk gasoline terminal with a gasoline throughput (total of all racks) less than 250,000 gallons per day; bulk gasoline terminal with a gasoline throughput (total of all racks) of 250,000 gallons per day or more; pipeline breakout station; or pipeline pumping station).

(vi) Date of report and beginning and ending dates of the reporting period. You are no longer required to provide the date of report when the report is submitted via CEDRI.

(vii) Statement by a responsible official, with that official's name, title, and signature, certifying the truth, accuracy, and completeness of the content of the report. If your report is submitted via CEDRI, the certifier's electronic signature during the submission process replaces the requirement in this paragraph (d)(1)(vii).

(2) For each thermal oxidation system used to comply with the provision in § 63.11092(e)(2)(i) by monitoring the combustion zone temperature, for each pressure CPMS used to comply with the requirements in § 60.502a(h) of this chapter, and for each vapor recovery system used to comply with the provisions in item 3 of table 3 to this subpart, report the following information for the CMS:

(i) For all instances when the temperature CPMS measured 3-hour rolling averages below the established operating limit or when the vapor collection system pressure exceeded the maximum loading pressure specified in § 60.502a(h) when liquid product was being loaded into gasoline cargo tanks or when the TOC CEMS measured 3-hour rolling average concentrations higher than the applicable emission limitation when the vapor recovery system was operating:

(A) The date and start time of the deviation.

(B) The duration of the deviation in hours.

(C) Each 3-hour rolling average combustion zone temperature, average pressure, or 3-hour rolling average TOC concentration during the deviation. For TOC concentration, indicate whether methane is excluded from the TOC concentration.

(D) A unique identifier for the CMS.

(E) The make, model number, and date of last calibration check of the CMS.

(F) The cause of the deviation and the corrective action taken.

(ii) For all instances that the temperature CPMS for measuring the combustion zone temperature or pressure CPMS was not operating or out of control when liquid product was loaded into gasoline cargo tanks, or the TOC CEMS was not operating or was out of control when the vapor recovery system was operating:

(A) The date and start time of the deviation.

(B) The duration of the deviation in hours.

(C) A unique identifier for the CMS.

(D) The make, model number, and date of last calibration check of the CMS.

(E) The cause of the deviation and the corrective action taken. For TOC CEMS outages where the limited alternative for vapor recovery systems in § 60.504a(e) of this chapter is used, the corrective action taken shall include an indication of the use of the limited alternative for vapor recovery systems in § 60.504a(e) of this chapter.

(F) For TOC CEMS outages where the limited alternative for vapor recovery systems in § 60.504a(e) of this chapter is used, report either an indication that there were no deviations from the operating limits when using the limited alternative or report the number of each of the following types of deviations that occurred during the use of the limited alternative for vapor recovery systems in § 60.504a(e) of this chapter.

(1) The number of adsorption cycles when the quantity of liquid product loaded in gasoline cargo tanks exceeded the operating limit established in § 60.504a(e)(1) of this chapter. Enter 0 if no deviations of this type.

(2) The number of desorption cycles when the vacuum pressure was below the average vacuum pressure as specified in § 60.504a(e)(2)(i) of this chapter. Enter 0 if no deviations of this type.

(3) The number of desorption cycles when the quantity of purge gas used was below the average quantity of purge gas as specified in § 60.504a(e)(2)(ii) of this chapter. Enter 0 if no deviations of this type.

(4) The number of desorption cycles when the duration of the vacuum/purge cycle was less than the average duration as specified in § 60.504a(e)(2)(iii) of this chapter. Enter 0 if no deviations of this type.

(3) For each thermal oxidation system used to comply with the provision in § 63.11092(e)(2)(ii) and each flare used to comply with the provision in item 2 of table 3 to this subpart, report:

(i) The date and start and end times for each of the following instances:

(A) Each 15-minute block during which there was at least one minute when gasoline vapors were routed to the flare and no pilot flame was present.

(B) Each period of 2 consecutive hours during which visible emissions exceeded a total of 5 minutes. Additionally, report the number of minutes for which visible emissions were observed during the observation or an estimate of the cumulative number of minutes in the 2-hour period for which emissions were visible based on best information available to the owner or operator.

(C) Each 15-minute period for which the applicable operating limits specified in § 63.670(d) through (f) were not met. You must identify the specific operating limit that was not met. Additionally, report the information in paragraphs (d)(3)(i)(C)(1) through (3) of this section, as applicable.

(1) If you use the loading rate operating limits as determined in § 60.502a(c)(3)(vii) of this chapter alone or in combination with the supplemental gas flow rate monitoring alternative in § 60.502a(c)(3)(viii) of this chapter, the required minimum ratio and the actual ratio of gasoline loaded to total product loaded for the rolling 15-minute period and, if applicable, the required minimum quantity and the actual quantity of gasoline loaded, in gallons, for the rolling 15-minute period.

(2) If you use the supplemental gas flow rate monitoring alternative in § 60.502a(c)(3)(viii) of this chapter, the required minimum supplemental gas flow rate and the actual supplemental gas flow rate including units of flow rates for the 15-minute block.

(3) If you use parameter monitoring systems other than those specified in paragraphs (d)(3)(i)(C)(1) and (2) of this section, the value of the net heating value operating parameter(s) during the deviation determined following the methods in § 63.670(k) through (n) as applicable.

(ii) The start date, start time, and duration in minutes for each period when “vapors displaced from gasoline cargo tanks during product loading” were routed to the flare or thermal oxidation system and the applicable monitoring was not performed.

(iii) For each instance reported under paragraphs (d)(3)(i) and (ii) of this section that involves CMS, report the following information:

(A) A unique identifier for the CMS.

(B) The make, model number, and date of last calibration check of the CMS.

(C) The cause of the deviation or downtime and the corrective action taken.

(4) For any instance in which liquid product was loaded into a gasoline cargo tank for which vapor tightness documentation required under § 63.11094(b) was not provided or available in the terminal's records, report:

(i) Cargo tank owner and address.

(ii) Cargo tank identification number.

(iii) Date and time liquid product was loaded into a gasoline cargo tank without proper documentation.

(iv) Date proper documentation was received or statement that proper documentation was never received.

(5) For each instance when liquid product was loaded into gasoline cargo tanks not using submerged filling, as defined in § 63.11100, not equipped with vapor collection or balancing equipment that is compatible with the terminal's vapor collection system or plant's vapor balancing system, or not properly connected to the terminal's vapor collection system or plant's vapor balancing system, report:

(i) Date and time of liquid product loading into gasoline cargo tank not using submerged filling, improperly equipped, or improperly connected.

(ii) The type of deviation (e.g., not submerged filling, incompatible equipment, not properly connected).

(iii) Cargo tank identification number.

(6) For each instance when gasoline was loaded between gasoline cargo tanks and storage tanks and the plant's vapor balancing system was not properly connected between the gasoline cargo tank and storage tank, report:

(i) Date and time of gasoline loading between a gasoline cargo tank and a storage tank that was not properly connected.

(ii) Cargo tank identification number and storage tank identification number.

(7) Report the following information for each leak inspection and each leak identified under § 63.11089(c) and § 60.503a(a)(2) of this chapter.

(i) For each leak detected during a leak inspection required under § 63.11089(c) and § 60.503a(a)(2) of this chapter, report:

(A) The date of inspection.

(B) The leak determination method (OGI or Method 21).

(C) The total number and type of equipment for which leaks were detected.

(D) The total number and type of equipment for which leaks were repaired within 15 calendar days.

(E) The total number and type of equipment for which no repair attempt was made within 5 calendar days of the leaks being identified.

(F) The total number and types of equipment placed on the delay of repair, as specified in § 60.502a(j)(8) of this chapter.

(ii) For leaks identified under § 63.11089(c) by audio/visual/olfactory methods during normal duties report:

(A) The total number and type of equipment for which leaks were identified.

(B) The total number and type of equipment for which leaks were repaired within 15 calendar days.

(C) The total number and type of equipment for which no repair attempt was made within 5 calendar days of the leaks being identified.

(D) The total number and type of equipment placed on the delay of repair, as specified in § 60.502a(j)(8) of this chapter.

(iii) The total number of leaks on the delay of repair list at the start of the reporting period.

(iv) The total number of leaks on the delay of repair list at the end of the reporting period.

(v) For each leak that was on the delay of repair list at any time during the reporting period, report:

(A) Unique equipment identification number.

(B) Type of equipment.

(C) Leak determination method (OGI, Method 21, or audio/visual/olfactory).

(D) The reason(s) why the repair was not feasible within 15 calendar days.

(E) If applicable, the date repair was completed.

(8) For each gasoline storage tank subject to requirements in item 2 of table 1 to this subpart, report:

(i) If you are complying with options 2(a), 2(b), or 2(d) in table 1 to this subpart, the information specified in § 60.115b(a) or (b) of this chapter or deviations in measured parameter values from the plan specified in § 60.115b(c) of this chapter, depending upon the control equipment installed, or, if you are complying with option 2(e) in table 1 to this subpart, the information specified in § 63.1066(b).

(ii) If you are complying with options 2(c) or 2(e) in table 1 to this subpart, for each deviation in LEL monitoring, report:

(A) Date and start and end times of the LEL monitoring, and the tank being monitored.

(B) Description of the monitoring event, e.g., monitoring conducted concurrent with visual inspection required under § 60.113b(a)(2) of this chapter or § 63.1063(d)(2); monitoring that occurred on a date other than the visual inspection required under § 60.113b(a)(2) or § 63.1063(d)(2) of this chapter; re-monitoring due to high winds; re-monitoring after repair attempt.

(C) Wind speed in miles per hour at the top of the tank on the date of LEL monitoring.

(D) The highest 5-minute rolling average reading during the monitoring event.

(E) Whether the floating roof was repaired, replaced, or taken out of gasoline service. If the floating roof was repaired or replaced, also report the information in paragraphs (d)(8)(ii)(A) through (D) of this section for each re-monitoring conducted to confirm the repair.

(9) If there were no deviations from the emission limitations, operating parameters, or work practice standards, then provide a statement that there were no deviations from the emission limitations, operating parameters, or work practice standards during the reporting period. If there were no periods during which a continuous monitoring system (including a CEMS or CPMS) was inoperable or out-of-control, then provide a statement that there were no periods during which a continuous monitoring system was inoperable or out-of-control during the reporting period.

(e) Requirements for semiannual report submissions. Each owner or operator of an affected source under this subpart shall submit semiannual compliance reports with the information specified in paragraph (c) or (d) of this section to the Administrator according to the requirements in § 63.13. Beginning on May 8, 2027, or once the report template for this subpart has been available on the CEDRI website (https://www.epa.gov/electronic-reporting-air-emissions/cedri) for one year, whichever date is later, you must submit all subsequent semiannual compliance reports using the appropriate electronic report template on the CEDRI website for this subpart and following the procedure specified in § 63.9(k), except any medium submitted through mail must be sent to the attention of the Gasoline Distribution Sector Lead. The date report templates become available will be listed on the CEDRI website. Unless the Administrator or delegated State agency or other authority has approved a different schedule for submission of reports, the report must be submitted by the deadline specified in this subpart, regardless of the method in which the report is submitted.

[89 FR 39380, May 8, 2024]

Other Requirements and Information

§ 63.11098 - What parts of the General Provisions apply to me?

Table 4 to this subpart shows which parts of the General Provisions apply to you.

[89 FR 39383, May 8, 2024]

§ 63.11099 - Who implements and enforces this subpart?

(a) This subpart can be implemented and enforced by the U.S. EPA or a delegated authority such as the applicable State, local, or tribal agency. If the U.S. EPA Administrator has delegated authority to a State, local, or tribal agency, then that agency, in addition to the U.S. EPA, has the authority to implement and enforce this subpart. Contact the applicable U.S. EPA Regional Office to find out if implementation and enforcement of this subpart is delegated to a State, local, or tribal agency.

(b) In delegating implementation and enforcement authority of this subpart to a State, local, or tribal agency under subpart E of this part, the authorities specified in paragraph (c) of this section are retained by the Administrator of U.S. EPA and cannot be transferred to the State, local, or tribal agency.

(c) The authorities that cannot be delegated to State, local, or Tribal agencies are as specified in paragraphs (c)(1) through (5) of this section.

(1) Approval of alternatives to the requirements in §§ 63.11086 through 63.11088 and § 63.11092. Any owner or operator requesting to use an alternative means of emission limitation for storage vessels in Table 1 to this subpart must follow either the provisions in § 60.114b of this chapter if you are complying with options 2(a), 2(b), or 2(c) in Table 1 to this subpart, or the provisions in § 63.1064 if you are complying with option 2(d) in Table 1 to this subpart.

(2) Approval of major alternatives to test methods under § 63.7(e)(2)(ii) and (f), as defined in § 63.90, and as required in this subpart.

(3) Approval of major alternatives to monitoring under § 63.8(f), as defined in § 63.90, and as required in this subpart.

(4) Approval of major alternatives to recordkeeping and reporting under § 63.10(f), as defined in § 63.90, and as required in this subpart.

(5) Approval of an alternative to any electronic reporting to the EPA required by this subpart.

[73 FR 1933, Jan. 10, 2008, as amended at 89 FR 39383, May 8, 2024]

§ 63.11100 - What definitions apply to this subpart?

As used in this subpart, all terms not defined herein shall have the meaning given them in the Clean Air Act (CAA), in subparts A, K, Ka, Kb, and XXa of part 60 of this chapter, or in subparts A, R, and WW of this part. All terms defined in both subpart A of part 60 of this chapter and subparts A, R, and WW of this part shall have the meaning given in subparts A, R, and WW of this part. For purposes of this subpart, definitions in this section supersede definitions in other parts or subparts. s in this section supersede definitions in other parts or subparts.

Administrator means the Administrator of the United States Environmental Protection Agency or his or her authorized representative (e.g., a State that has been delegated the authority to implement the provisions of this subpart).

Bulk gasoline plant means any gasoline storage and distribution facility that receives gasoline by pipeline, ship or barge, or cargo tank, and subsequently loads the gasoline into gasoline cargo tanks for transport to gasoline dispensing facilities, and has a gasoline throughput of less than 20,000 gallons per day. Gasoline throughput shall be the maximum calculated design throughput as may be limited by compliance with an enforceable condition under Federal, State, or local law, and discoverable by the Administrator and any other person.

Bulk gasoline terminal means:

(1) Prior to May 8, 2027, any gasoline storage and distribution facility that receives gasoline by pipeline, ship or barge, or cargo tank and has a gasoline throughput of 20,000 gallons per day or greater. Gasoline throughput shall be the maximum calculated design throughput as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.

(2) On or after May 8, 2027, any gasoline facility which receives gasoline by pipeline, ship, barge, or cargo tank and subsequently loads all or a portion of the gasoline into gasoline cargo tanks for transport to bulk gasoline plants or gasoline dispensing facilities and has a gasoline throughput of 20,000 gallons per day (75,700 liters per day) or greater. Gasoline throughput shall be the maximum calculated design throughput for the facility as may be limited by compliance with an enforceable condition under Federal, State, or local law and discoverable by the Administrator and any other person.

Equipment means each valve, pump, pressure relief device, sampling connection system, open-ended valve or line, and flange or other connector in the gasoline liquid transfer and vapor collection systems. This definition also includes the entire vapor processing system except the exhaust port(s) or stack(s).

Flare means a thermal combustion device using an open or shrouded flame (without full enclosure) such that the pollutants are not emitted through a conveyance suitable to conduct a performance test.

Gasoline means any petroleum distillate or petroleum distillate/alcohol blend having a Reid vapor pressure of 4.0 pounds per square inch (27.6 kilopascals) or greater, which is used as a fuel for internal combustion engines.

Gasoline cargo tank means a delivery tank truck or railcar which is loading gasoline or which has loaded gasoline on the immediately previous load.

Gasoline storage tank or vessel means each tank, vessel, reservoir, or container used for the storage of gasoline, but does not include:

(1) Frames, housing, auxiliary supports, or other components that are not directly involved in the containment of gasoline or gasoline vapors;

(2) Subsurface caverns or porous rock reservoirs;

(3) Oil/water separators and sumps, including butane blending sample recovery tanks, used to collect drained material such that it can be pumped to storage or back into a process; or

(4) Tanks or vessels permanently attached to mobile sources such as trucks, railcars, barges, or ships.

In gasoline service means that a piece of equipment is used in a system that transfers gasoline or gasoline vapors.

Monthly means once per calendar month at regular intervals of no less than 28 days and no more than 35 days.

Operating parameter value means a value for an operating or emission parameter of the vapor processing system (e.g., temperature) which, if maintained continuously by itself or in combination with one or more other operating parameter values, determines that an owner or operator has complied with the applicable emission standard. The operating parameter value is determined using the procedures specified in § 63.11092(b) and (e).

Pipeline breakout station means:

(1) Prior to May 8, 2027, a facility along a pipeline containing storage vessels used to relieve surges or receive and store gasoline from the pipeline for reinjection and continued transportation by pipeline or to other facilities.

(2) On or after May 8, 2027, a facility along a pipeline containing storage vessels used to relieve surges or receive and store gasoline from the pipeline for reinjection and continued transportation by pipeline to other facilities. Pipeline breakout stations do not have loading racks where gasoline is loaded into cargo tanks. If any gasoline is loaded into cargo tanks, the facility is a bulk gasoline terminal for the purposes of this subpart provided the facility-wide gasoline throughput (including pipeline throughput) exceeds the limits specified for bulk gasoline terminals.

Pipeline pumping station means a facility along a pipeline containing pumps to maintain the desired pressure and flow of product through the pipeline, and not containing gasoline loading racks or gasoline storage tanks other than surge control tanks.

Submerged filling means, for the purposes of this subpart, the filling of a gasoline cargo tank or a stationary storage tank through a submerged fill pipe whose discharge is no more than the applicable distance specified in § 63.11086(a) from the bottom of the tank. Bottom filling of gasoline cargo tanks or storage tanks is included in this definition.

Surge control tank or vessel means, for the purposes of this subpart, those tanks or vessels used only for controlling pressure in a pipeline system during surges or other variations from normal operations.

Thermal oxidation system means an enclosed combustion device used to mix and ignite fuel, air pollutants, and air to provide a flame to heat and oxidize hazardous air pollutants. Auxiliary fuel may be used to heat air pollutants to combustion temperatures. Thermal oxidation systems emit pollutants through a conveyance suitable to conduct a performance test.

Vapor collection-equipped gasoline cargo tank means a gasoline cargo tank that is outfitted with the equipment necessary to transfer vapors, displaced during the loading of gasoline into the cargo tank, to a vapor processor system.

Vapor-tight gasoline cargo tank means a gasoline cargo tank which has demonstrated within the 12 preceding months that it meets the annual certification test requirements in § 63.11092(f).

[73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4178, Jan. 24, 2011; 89 FR 39383, May 8, 2024]

- Table 1 to Subpart BBBBBB of Part 63—Applicability Criteria, Emission Limits, and Management Practices for Storage Tanks

Table 1 to Subpart BBBBBB of Part 63—Applicability Criteria, Emission Limits, and Management Practices for Storage Tanks

If you own or operate . . . Then you must . . . 1. A gasoline storage tank meeting either of the following conditions:
(i) a capacity of less than 75 cubic meters (m 3); or
(ii) a capacity of less than 151 m 3 and a gasoline throughput of 480 gallons per day or less. Gallons per day is calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365
(a) Equip each gasoline storage tank with a fixed roof that is mounted to the storage tank in a stationary manner, and maintain all openings in a closed position at all times when not in use; and
(b) No later than the dates specified in § 63.11083, all pressure relief devices on each gasoline storage tank must be set to no less than 18 inches of water at all times to minimize breathing losses.
2. A gasoline storage tank with a capacity of greater than or equal to 75 m 3 and not meeting any of the criteria specified in item 1 of this tableDo the following:
(a) Reduce emissions of total organic HAP or TOC by 95 weight-percent with a closed vent system and control device, as specified in § 60.112b(a)(3) of this chapter; or
(b) Equip each internal floating roof gasoline storage tank according to the requirements in § 60.112b(a)(1) of this chapter, except for the secondary seal requirements under § 60.112b(a)(1)(ii)(B) and the requirements in § 60.112b(a)(1)(iv) through (ix) of this chapter; and
(c) No later than the dates specified in § 63.11083, equip, maintain, and operate each internal floating roof control system to maintain the vapor concentration within the storage tank above the floating roof at or below 25 percent of the LEL on a 5-minute rolling average basis without the use of purge gas, which may require additional controls beyond those specified in item 2(b) of this table; and
(d) Equip each external floating roof gasoline storage tank according to the requirements in § 60.112b(a)(2) of this chapter, except that the requirements of § 60.112b(a)(2)(ii) of this chapter shall only be required if such storage tank does not currently meet the requirements of § 60.112b(a)(2)(i) of this chapter; by the dates specified in § 63.11083, all external floating roofs must meet the requirements of § 60.112b(a)(2)(ii) of this chapter; or
(e) Equip and operate each internal and external floating roof gasoline storage tank according to the applicable requirements in § 63.1063(a)(1) and (b), except for the secondary seal requirements under § 63.1063(a)(1)(i)(C) and (D), and equip each external floating roof gasoline storage tank according to the requirements of § 63.1063(a)(2) by the dates specified in § 63.11087(b) if such storage tank does not currently meet the requirements of § 63.1063(a)(1); by the dates specified in § 63.11083, all external floating roofs must meet the requirements of § 63.1063(a)(2); and
(f) No later than the dates specified in § 63.11083, equip, maintain, and operate each internal floating roof control system to maintain the vapor concentration within the storage tank above the floating roof at or below 25 percent of the LEL on a 5-minute rolling average basis without the use of purge gas, which may require additional controls beyond those specified in item 2(e) of this table.
3. A surge control tankEquip each tank with a fixed roof that is mounted to the tank in a stationary manner and with a pressure/vacuum vent with a positive cracking pressure of no less than 0.50 inches of water. Maintain all openings in a closed position at all times when not in use.
[76 FR 4179, Jan. 24, 2011, as amended at 89 FR 39384, May 8, 2024]

- Table 2 to Subpart BBBBBB of Part 63—Applicability Criteria, Emission Limits, and Management Practices for Loading Racks

Table 2 to Subpart BBBBBB of Part 63—Applicability Criteria, Emission Limits, and Management Practices for Loading Racks

If you own or operate . . . Then you must . . . 1. A bulk gasoline terminal loading rack(s) with a gasoline throughput (total of all racks) of 250,000 gallons per day, or greater (“large bulk gasoline terminal”). Gallons per day is calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365(a) Equip your loading rack(s) with a vapor collection system designed and operated to collect the TOC vapors displaced from cargo tanks during product loading; and
(b) Reduce emissions of TOC to less than or equal to 80 mg/l of gasoline loaded into gasoline cargo tanks at the loading rack; and
(c) No later than the dates specified in § 63.11083, reduce emissions of TOC to the applicable limits in table 3 to this subpart. The requirements in item 1(b) do not apply when demonstrating compliance with this item; and
(d) Design and operate the vapor collection system to prevent any TOC vapors collected at one loading rack or lane from passing through another loading rack or lane to the atmosphere; and
(e) Limit the loading of gasoline into gasoline cargo tanks that are vapor tight using the procedures specified in § 60.502(e) through (j) of this chapter. For the purposes of this section, the term “tank truck” as used in § 60.502(e) through (j) means “gasoline cargo tank” as defined in § 63.11100; and
(f) No later than the dates specified in § 63.11083, limit the loading of liquid product into gasoline cargo tanks using the procedures specified in § 60.502a(e) through (i) of this chapter and in § 63.11092(g) and (h). The requirements in item 1(e) do not apply when demonstrating compliance with this item.
2. A bulk gasoline terminal loading rack(s) with a gasoline throughput (total of all racks) of less than 250,000 gallons per day. Gallons per day is calculated by summing the current day's throughput, plus the throughput for the previous 364 days, and then dividing that sum by 365(a) Use submerged filling with a submerged fill pipe that is no more than 6 inches from the bottom of the cargo tank; and
(b) Make records available within 24 hours of a request by the Administrator to document your gasoline throughput.
(c) No later than the dates specified in § 63.11083, limit the loading of gasoline into gasoline cargo tanks that are vapor tight using the procedures specified in § 60.502a(e) of this chapter and in § 63.11092(g).
[76 FR 4179, Jan. 24, 2011, as amended at 89 FR 39385, May 8, 2024]

- Table 3 to Subpart BBBBBB of Part 63—Applicability of General Provisions

Table 3 to Subpart BBBBBB of Part 63—Emission Limitations and Requirements for Large Bulk Gasoline Terminals Based on Control System Used

If you operate . . . Then you must . . . 1. A thermal oxidation system(a) Reduce emissions of TOC to less than or equal to 35 mg/l of liquid product loaded into gasoline cargo tanks at the loading rack; and
(b) Continuously meet the applicable operating limit as specified in § 63.11092(e)(2).
2. A flareOperate the flare following the applicable requirements specified in § 60.502a(c)(3) of this chapter. 3. A carbon adsorption system, refrigerated condenser, or other vapor recovery system.(a) Reduce emissions of TOC to less than or equal to 19,200 parts per million by volume as propane determined on a 3-hour rolling average considering all periods when the vapor recovery system is capable of processing gasoline vapors, including periods when liquid product is being loaded, during carbon bed regeneration, and when preparing the beds for reuse.
(b) Operate the vapor recovery system to minimize air or nitrogen intrusion except as needed for the system to operate as designed for the purpose of removing VOC from the adsorption media or to break vacuum in the system and bring the system back to atmospheric pressure. Consistent with § 63.4, the use of diluents to achieve compliance with a relevant standard based on the concentration of a pollutant in the effluent discharged to the atmosphere is prohibited.
[73 FR 1933, Jan. 10, 2008, as amended at 76 FR 4180, Jan. 24, 2011; 85 FR 73919, Nov. 19, 2020; 89 FR 39386, May 8, 2024]

- Table 4 to Subpart BBBBBB of Part 63—Applicability of General Provisions

Table 4 to Subpart BBBBBB of Part 63—Applicability of General Provisions

Citation Subject Brief description Applies to this subpart § 63.1ApplicabilityInitial applicability determination; applicability after standard established; permit requirements; extensions, notificationsYes, specific requirements given in § 63.11081. § 63.1(c)(2)Title V permitRequirements for obtaining a title V permit from the applicable permitting authorityYes, § 63.11081(b) exempts identified area sources from the obligation to obtain title V operating permits. § 63.2DefinitionsDefinitions for standards in this partYes, additional definitions in § 63.11100. § 63.3Units and AbbreviationsUnits and abbreviations for standards under this partYes. § 63.4Prohibited Activities and CircumventionProhibited activities; circumvention, severabilityYes. § 63.5Construction/ReconstructionApplicability; applications; approvalsYes. § 63.6(a)Compliance with Standards/Operation & Maintenance ApplicabilityGeneral Provisions apply unless compliance extension; General Provisions apply to area sources that become majorYes. § 63.6(b)(1) through (4)Compliance Dates for New and Reconstructed SourcesDates standards apply for new and reconstructed sourcesYes. § 63.6(b)(5)NotificationMust notify if commenced construction or reconstruction after proposalYes. § 63.6(b)(6)[Reserved].§ 63.6(b)(7)Compliance Dates for New and Reconstructed Area Sources that Become MajorArea sources that become major must comply with major source standards immediately upon becoming major, regardless of whether required to comply when they were an area sourceNo. § 63.6(c)(1) and (2)Compliance Dates for Existing SourcesComply according to date in this subpartNo, § 63.11083 specifies the compliance dates. § 63.6(c)(3) and (4)[Reserved].§ 63.6(c)(5)Compliance Dates for Existing Area Sources that Become MajorArea sources that become major must comply with major source standards by date indicated in this subpart or by equivalent time period (e.g., 3 years)No. § 63.6(d)[Reserved].§ 63.6(e)(1)(i)General duty to minimize emissionsOperate to minimize emissions at all times; information Administrator will use to determine if operation and maintenance requirements were metNo. See § 63.11085 for general duty requirement. § 63.6(e)(1)(ii)Requirement to correct malfunctions as soon as possibleOwner or operator must correct malfunctions as soon as possibleNo. § 63.6(e)(2)[Reserved].§ 63.6(e)(3)Startup, Shutdown, and Malfunction (SSM) planRequirement for SSM plan; content of SSM plan; actions during SSMNo. § 63.6(f)(1)Compliance Except During SSMYou must comply with emission standards at all times except during SSMNo. § 63.6(f)(2) and (3)Methods for Determining ComplianceCompliance based on performance test, operation and maintenance plans, records, inspectionYes. § 63.6(g)(1) through (3)Alternative StandardProcedures for getting an alternative standardYes. § 63.6(h)(1)Compliance with Opacity/VE StandardsYou must comply with opacity/VE standards at all times except during SSMNo. § 63.6(h)(2)(i)Determining Compliance with Opacity/VE StandardsIf standard does not state test method, use EPA Method 9 for opacity in appendix A to part 60 of this chapter and EPA Method 22 for VE in appendix A to part 60 of this chapterNo. § 63.6(h)(2)(ii)[Reserved].§ 63.6(h)(2)(iii)Using Previous Tests to Demonstrate Compliance with Opacity/VE StandardsCriteria for when previous opacity/VE testing can be used to show compliance with this subpartNo. § 63.6(h)(3)[Reserved].§ 63.6(h)(4)Notification of Opacity/VE Observation DateMust notify Administrator of anticipated date of observationNo. § 63.6(h)(5)(i) and (iii) through (v)Conducting Opacity/VE ObservationsDates and schedule for conducting opacity/VE observationsNo. § 63.6(h)(5)(ii)Opacity Test Duration and Averaging TimesMust have at least 3 hours of observation with 30 6-minute averagesNo. § 63.6(h)(6)Records of Conditions During Opacity/VE ObservationsMust keep records available and allow Administrator to inspectNo. § 63.6(h)(7)(i)Report Continuous Opacity Monitoring System (COMS) Monitoring Data from Performance TestMust submit COMS data with other performance test dataNo. § 63.6(h)(7)(ii)Using COMS Instead of EPA Method 9Can submit COMS data instead of EPA Method 9 results even if this subpart requires EPA Method 9 in appendix A of part 60 of this chapter, but must notify Administrator before performance testNo. § 63.6(h)(7)(iii)Averaging Time for COMS During Performance TestTo determine compliance, must reduce COMS data to 6-minute averagesNo. § 63.6(h)(7)(iv)COMS RequirementsOwner/operator must demonstrate that COMS performance evaluations are conducted according to § 63.8(e); COMS are properly maintained and operated according to § 63.8(c) and data quality as § 63.8(d)No. § 63.6(h)(7)(v)Determining Compliance with Opacity/VE StandardsCOMS is probable but not conclusive evidence of compliance with opacity standard, even if EPA Method 9 (in appendix A to part 60 of this chapter) observation shows otherwise. Requirements for COMS to be probable evidence-proper maintenance, meeting Performance Specification 1 in appendix B to part 60 of this chapter, and data have not been alteredNo. § 63.6(h)(8)Determining Compliance with Opacity/VE StandardsAdministrator will use all COMS, EPA Method 9 (in appendix A to part 60 of this chapter), and EPA Method 22 (in appendix A to part 60 of this chapter) results, as well as information about operation and maintenance to determine complianceNo. § 63.6(h)(9)Adjusted Opacity StandardProcedures for Administrator to adjust an opacity standardNo. § 63.6(i)(1) through (14)Compliance ExtensionProcedures and criteria for Administrator to grant compliance extensionYes. § 63.6(j)Presidential Compliance ExemptionPresident may exempt any source from requirement to comply with this subpartYes. § 63.7(a)(2)Performance Test DatesDates for conducting initial performance testing; must conduct 180 days after compliance dateYes. § 63.7(a)(3)Section 114 AuthorityAdministrator may require a performance test under CAA section 114 at any timeYes. § 63.7(a)(4)Force MajeureProvisions for delayed performance tests due to force majeureYes. § 63.7(b)(1)Notification of Performance TestMust notify Administrator 60 days before the testYes. § 63.7(b)(2)Notification of Re-schedulingIf have to reschedule performance test, must notify Administrator of rescheduled date as soon as practicable and without delayYes. § 63.7(c)Quality Assurance (QA)/Test PlanRequirement to submit site-specific test plan 60 days before the test or on date Administrator agrees with; test plan approval procedures; performance audit requirements; internal and external QA procedures for testingYes. § 63.7(d)Testing FacilitiesRequirements for testing facilitiesYes. § 63.7(e)(1)Conditions for Conducting Performance TestsPerformance test must be conducted under representative conditionsNo, § 63.11092(i) specifies conditions for conducting performance tests. § 63.7(e)(2)Conditions for Conducting Performance TestsMust conduct according to this subpart and EPA test methods unless Administrator approves alternativeYes. § 63.7(e)(3)Test Run DurationMust have three test runs of at least 1 hour each; compliance is based on arithmetic mean of three runs; conditions when data from an additional test run can be usedYes, except for testing conducted under § 63.11092(a) and (e). § 63.7(f)Alternative Test MethodProcedures by which Administrator can grant approval to use an intermediate or major change, or alternative to a test methodYes. § 63.7(g)Performance Test Data AnalysisMust include raw data in performance test report; must submit performance test data 60 days after end of test with the notification of compliance status; keep data for 5 yearsYes, except this subpart specifies how and when the performance test and performance evaluation results are reported. § 63.7(h)Waiver of TestsProcedures for Administrator to waive performance testYes. § 63.8(a)(1)Applicability of Monitoring RequirementsSubject to all monitoring requirements in standardYes. § 63.8(a)(2)Performance SpecificationsPerformance specifications in appendix B to part 60 of this chapter applyYes. § 63.8(a)(3)[Reserved].§ 63.8(a)(4)Monitoring of FlaresMonitoring requirements for flares in § 63.11 applyYes. § 63.8(b)(1)MonitoringMust conduct monitoring according to standard unless Administrator approves alternativeYes. § 63.8(b)(2) and (3)Multiple Effluents and Multiple Monitoring SystemsSpecific requirements for installing monitoring systems; must install on each affected source or after combined with another affected source before it is released to the atmosphere provided the monitoring is sufficient to demonstrate compliance with the standard; if more than one monitoring system on an emission point, must report all monitoring system results, unless one monitoring system is a backupYes. § 63.8(c)(1) introductory textMonitoring System Operation and MaintenanceMaintain monitoring system in a manner consistent with good air pollution control practicesYes. § 63.8(c)(1)(i)Operation and Maintenance of CMSMust maintain and operate each CMS as specified in § 63.6(e)(1)No. § 63.8(c)(1)(ii)Operation and Maintenance of CMSMust keep parts for routine repairs readily availableYes. § 63.8(c)(1)(iii)Operation and Maintenance of CMSRequirement to develop SSM Plan for CMSNo. § 63.8(c)(2) through (8)CMS RequirementsMust install to get representative emission or parameter measurements; must verify operational status before or at performance testYes. § 63.8(d)(1) and (2)CMS Quality ControlRequirements for CMS quality control, including calibration, etc.Yes. § 63.8(d)(3)CMS Quality Control RecordsMust keep quality control plan on record for 5 years; keep old versions for 5 years after revisionsNo. This subpart specifies CMS records requirements. § 63.8(e)CMS Performance EvaluationNotification, performance evaluation test plan, reportsYes, except this subpart specifies how and when the performance evaluation results are reported. § 63.8(f)(1) through (5)Alternative Monitoring MethodProcedures for Administrator to approve alternative monitoringYes. § 63.8(f)(6)Alternative to Relative Accuracy TestProcedures for Administrator to approve alternative relative accuracy tests for CEMSYes. § 63.8(g)Data ReductionCOMS 6-minute averages calculated over at least 36 evenly spaced data points; CEMS 1 hour averages computed over at least 4 equally spaced data points; data that cannot be used in averageYes. § 63.9(a)Notification RequirementsApplicability and State delegationYes. § 63.9(b)(1), (2), (4), and (5)Initial NotificationsSubmit notification of being subject to standard; notification of intent to construct/reconstruct, notification of commencement of construction/reconstruction, notification of startup; contents of eachYes. § 63.9(b)(3)[Reserved].§ 63.9(c)Request for Compliance ExtensionCan request if cannot comply by date or if installed best available control technology or lowest achievable emission rateYes. § 63.9(d)Notification of Special Compliance Requirements for New SourcesNotification for new sources subject to special compliance requirementsYes. § 63.9(e)Notification of Performance TestNotify Administrator 60 days priorYes. § 63.9(f)Notification of VE/Opacity TestNotify Administrator 30 days priorNo. § 63.9(g)Additional Notifications When Using CMSNotification of performance evaluation; notification about use of COMS data; notification that exceeded criterion for relative accuracy alternativeYes, however, there are no opacity standards. § 63.9(h)(1) through (3), (5), and (6)Notification of Compliance StatusContents due 60 days after end of performance test or other compliance demonstration, except for opacity/VE, which are due 30 days after; when to submit to Federal vs. State authorityYes, except as specified in § 63.11095(c). § 63.9(h)(4)[Reserved].§ 63.9(i)Adjustment of Submittal DeadlinesProcedures for Administrator to approve change when notifications must be submittedYes. § 63.9(j)Change in Previous InformationMust submit within 15 days after the changeYes. § 63.9(k)NotificationsElectronic reporting proceduresYes. § 63.10(a)Recordkeeping/ReportingApplies to all, unless compliance extension; when to submit to Federal vs. State authority; procedures for owners of more than one sourceYes. § 63.10(b)(1)Recordkeeping/ReportingGeneral requirements; keep all records readily available; keep for 5 yearsYes. § 63.10(b)(2)(i)Records related to SSMRecordkeeping of occurrence and duration of startups and shutdownsNo. § 63.10(b)(2)(ii)Records related to SSMRecordkeeping of malfunctionsNo. See § 63.11094(k) for recordkeeping requirements for deviations. § 63.10(b)(2)(iii)Maintenance recordsRecordkeeping of maintenance on air pollution control and monitoring equipmentYes. § 63.10(b)(2)(iv)Records Related to SSMActions taken to minimize emissions during SSMNo. § 63.10(b)(2)(v)Records Related to SSMActions taken to minimize emissions during SSMNo. § 63.10(b)(2)(vi) through (xi)CMS RecordsMalfunctions, inoperative, out-of-control periodsYes. § 63.10(b)(2)(xii)RecordsRecords when under waiverYes. § 63.10(b)(2)(xiii)RecordsRecords when using alternative to relative accuracy testYes. § 63.10(b)(2)(xiv)RecordsAll documentation supporting initial notification and notification of compliance statusYes. § 63.10(b)(3)RecordsApplicability determinationsYes. § 63.10(c)RecordsAdditional records for CMSNo. This subpart specifies CMS records. § 63.10(d)(1)General Reporting RequirementsRequirement to reportYes. § 63.10(d)(2)Report of Performance Test ResultsWhen to submit to Federal or State authorityNo. This subpart specifies how and when the performance test results are reported. § 63.10(d)(3)Reporting Opacity or VE ObservationsWhat to report and whenNo. § 63.10(d)(4)Progress ReportsMust submit progress reports on schedule if under compliance extensionYes. § 63.10(d)(5)SSM ReportsContents and submissionNo. § 63.10(e)(1) and (2)Additional CMS ReportsMust report results for each CEMS on a unit; written copy of CMS performance evaluation; 2-3 copies of COMS performance evaluationNo. § 63.10(e)(3)(i) through (iii)ReportsSchedule for reporting excess emissionsNo. § 63.10(e)(3)(iv) and (v)Excess Emissions ReportsRequirement to revert to quarterly submission if there is an excess emissions and parameter monitor exceedances (now defined as deviations); provision to request semiannual reporting after compliance for 1 year; submit report by 30th day following end of quarter or calendar half; if there has not been an exceedance or excess emissions (now defined as deviations), report contents in a statement that there have been no deviations; must submit report containing all of the information in §§ 63.8(c)(7) and (8) and 63.10(c)(5) through (13)No. § 63.10(e)(3)(vi) through (viii)Excess Emissions Report and Summary ReportRequirements for reporting excess emissions for CMS; requires all of the information in §§ 63.8(c)(7) and (8) and 63.10(c)(5) through (13)No. § 63.10(e)(4)Reporting COMS DataMust submit COMS data with performance test dataNo. This subpart specifies COMS reporting. § 63.10(f)Waiver for Recordkeeping/ReportingProcedures for Administrator to waiveYes. § 63.11(a)ApplicabilitySpecifies applicability of control device and work practice requirements within § 63.11Yes. § 63.11(b)FlaresRequirements for flaresYes, except these provisions no longer apply for flares used to comply with the flare provisions in item 2 of table 3 to this subpart. § 63.11(c) through (e)Alternative Work Practice for Monitoring Equipment for LeaksRequirements for using optical gas imaging for EPA Method 21 monitoringYes, except these provisions do not apply to monitoring required under § 63.11092(a)(1)(i) or (e)(1) and these provisions no longer apply upon compliance with the provisions in § 63.11089(c). § 63.12DelegationState authority to enforce standardsYes. § 63.13AddressesAddresses where reports, notifications, and requests are sentYes. § 63.14Incorporations by ReferenceTest methods incorporated by referenceYes. § 63.15Availability of InformationPublic and confidential informationYes. § 63.16Performance Track ProvisionsSpecial reporting provision for Performance Track member facilities.Yes.
[89 FR 39386, May 8, 2024]