Collapse to view only § 228.104 - Consideration of requests to modify, waive, or grant exceptions to lease stipulations.

Leasing

§ 228.102 - Leasing analyses and decisions.

(a) Compliance with the National Environmental Policy Act of 1969. In analyzing lands for leasing, the authorized Forest officer shall comply with the National Environmental Policy Act of 1969, implementing regulations at 43 CFR parts 1500-1508, and Forest Service implementing policies and procedures set forth in Forest Service Manual chapter 1950 and Forest Service Handbook 1909.15.

(b) Scheduling analysis of available lands. Within 6 months of April 20, 1990, Forest Supervisors shall develop, in cooperation with the Bureau of Land Management and with public input, a schedule for analyzing lands under their jurisdiction that have not been already analyzed for leasing. The Forest Supervisors shall revise or make additions to the schedule at least annually. In scheduling lands for analysis, the authorized Forest officer shall identify and exclude from further review the following lands which are legally unavailable for leasing:

(1) Lands withdrawn from mineral leasing by an act of Congress or by an order of the Secretary of the Interior;

(2) Lands recommended for wilderness allocation by the Secretary of Agriculture;

(3) Lands designated by statute as wilderness study areas, unless oil and gas leasing is specifically allowed by the statute designating the study area; and

(4) Lands within areas allocated for wilderness or further planning in Executive Communication 1504, Ninety-Sixth Congress (House Document No. 96-119), unless such lands subsequently have been allocated to uses other than wilderness by an approved Forest land and resource management plan or have been released to uses other than wilderness by an act of Congress.

(c) Leasing analyses. The leasing analysis shall be conducted by the authorized Forest officer in accordance with the requirements of 36 CFR part 219 (Forest land and resource management planning) and/or, as appropriate, through preparation of NEPA documents. As part of the analysis, the authorized Forest officer shall:

(1) Identify on maps those areas that will be:

(i) Open to development subject to the terms and conditions of the standard oil and gas lease form (including an explanation of the typical standards and objectives to be enforced under the standard lease terms);

(ii) Open to development but subject to constraints that will require the use of lease stipulations such as those prohibiting surface use on areas larger than 40 acres or such other standards as may be developed in the plan for stipulation use (with discussion as to why the constraints are necessary and justifiable); and

(iii) Closed to leasing, distinguishing between those areas that are being closed through exercise of management direction, and those closed by law, regulation, etc.

(2) Identify alternatives to the areas listed in paragraph (c)(1) of this section, including that of not allowing leasing.

(3) Project the type/amount of post-leasing activity that is reasonably foreseeable as a consequence of conducting a leasing program consistent with that described in the proposal and for each alternative.

(4) Analyze the reasonable foreseeable impacts of post-leasing activity projected under paragraph (c)(3) of this section.

(d) Area or Forest-wide leasing decisions (lands administratively available for leasing). Upon completion of the leasing analysis, the Regional Forest shall promptly notify the Bureau of Land Management as to the area or Forest-wide leasing decisions that have been made, that is, identify lands which have been found administratively available for leasing.

(e) Leasing decisions for specific lands. At such time as specific lands are being considered for leasing, the Regional Forester shall review the area or Forest-wide leasing decision and shall authorize the Bureau of Land Management to offer specific lands for lease subject to:

(1) Verifying that oil and gas leasing of the specific lands has been adequately addressed in a NEPA document, and is consistent with the Forest land and resource management plan. If NEPA has not been adequately addressed, or if there is significant new information or circumstances as defined by 40 CFR 1502.9 requiring further environmental analysis, additional environment analysis shall be done before a leasing decision for specific lands will be made. If there is inconsistency with the Forest land and resource management plan, no authorization for leasing shall be given unless the plan is amended or revised.

(2) Ensuring that conditions of surface occupancy identified in § 228.102(c)(1) are properly included as stipulations in resulting leases.

(3) Determining that operations and development could be allowed somewhere on each proposed lease, except where stipulations will prohibit all surface occupancy.

[55 FR 10444, Mar. 21, 1990, as amended at 56 FR 56157, Nov. 1, 1991]

§ 228.103 - Notice of appeals of decisions.

The authorized Forest officer shall promptly notify the Bureau of Land Management if appeals of either an area or Forest-wide leasing decision or a leasing decision for specific lands are filed during the periods provided for under 36 CFR part 217.

§ 228.104 - Consideration of requests to modify, waive, or grant exceptions to lease stipulations.

(a) General. An operator submitting a surface use plan of operations may request the authorized Forest officer to authorize the Bureau of Land Management to modify (permanently change), waive (permanently remove), or grant an exception (case-by-case exemption) to a stipulation included in a lease at the direction of the Forest Service. The person making the request is encouraged to submit any information which might assist the authorized Forest officer in making a decision.

(b) Review. The authorized Forest officer shall review any information submitted in support of the request and any other pertinent information.

(1) As part of the review, consistent with 30 U.S.C. 226 (f)-(g), the authorized Forest officer shall ensure compliance with the National Environmental Policy Act of 1969 (42 U.S.C. 4331 et seq.) and any other applicable laws, and shall ensure preparation of any appropriate environmental documents.

(2) The authorized Forest officer may authorize the Bureau of Land Management to modify, waive, or grant an exception to a stipulation if:

(i) The action would be consistent with applicable Federal laws;

(ii) The action would be consistent with the current forest land and resource management plan;

(iii) The management objectives which led the Forest Service to require the inclusion of the stipulation in the lease can be met without restricting operations in the manner provided for by the stipulation given the change in the present condition of the surface resources involved, or given the nature, location, timing, or design of the proposed operations; and

(iv) The action is acceptable to the authorized Forest officer based upon a review of the environmental consequences.

(c) Other agency stipulations. If a stipulation was included in a lease by the Forest Service at the request of another agency, the authorized Forest officer shall consult with that agency prior to authorizing modification, waiver, or exception.

(d) Notice of decision. (1) When the review of a stipulation modification, waiver, or exception request has been completed and the authorized Forest officer has reached a decision, the authorized Forest officer shall promptly notify the operator and the appropriate Bureau of Land Management office, in writing, of the decision to grant, or grant with additional conditions, or deny the request.

(2) Any decision to modify, waive, or grant an exception to a lease stipulation shall be subject to administrative appeal only in conjunction with an appeal of a decision on a surface use plan of operation or supplemental surface use plan of operation.

§ 228.100 - Scope and applicability.

(a) Scope. This subpart sets forth the rules and procedures by which the Forest Service of the United States Department of Agriculture will carry out its statutory responsibilities in the issuance of Federal oil and gas leases and management of subsequent oil and gas operations on National Forest System lands, for approval and modification of attendant surface use plans of operations, for monitoring of surface disturbing operations on such leases, and for enforcement of surface use requirements and reclamation standards.

(b) Applicability. The rules of this subpart apply to leases on National Forest System lands and to operations that are conducted on Federal oil and gas leases on National Forest System lands as of April 20, 1990.

(c) Applicability of other rules. Surface uses associated with oil and gas prospecting, development, production, and reclamation activities, that are conducted on National Forest System lands outside a leasehold must receive prior authorization from the Forest Service. Such activities are subject to the regulations set forth elsewhere in 36 CFR chapter II, including but not limited to the regulations set forth in 36 CFR parts 251, subpart B, and 261.

§ 228.101 - Definitions.

For the purposes of this subpart, the terms listed in this section have the following meaning:

Authorized Forest officer. The Forest Service employee delegated the authority to perform a duty described in these rules. Generally, a Regional Forester, Forest Supervisor, District Ranger, or Minerals Staff Officer, depending on the scope and level of the duty to be performed.

Compliance Officer. The Deputy Chief, or the Associate Deputy Chiefs, National Forest System or the line officer designated to act in the absence of the Deputy Chief.

Leasehold. The area described in a Federal oil and gas lease, communitized, or unitized area.

Lessee. A person or entity holding record title in a lease issued by the United States.

National Forest System. All National Forest lands reserved or withdrawn from the public domain of the United States, all National Forest lands acquired through purchase, exchange, donation, or other means, the National Grasslands and land utilization projects administered under title III of the Bankhead-Jones Farm Tenant Act (7 U.S.C. 1010 et seq.), and other lands, waters, or interests therein which are administered by the Forest Service or are designated for administration through the Forest Service as a part of the system (16 U.S.C. 1609).

Notices to Lessees, Transferees, and Operators. A written notice issued by the authorized Forest officer. Notices to Lessees, Transferees, and Operators implement the regulations in this subpart and serve as instructions on specific item(s) of importance within a Forest Service Region, National Forest, or Ranger District.

Onshore Oil and Gas Order. A formal numbered order issued by or signed by the Chief of the Forest Service that implements and supplements the regulations in this subpart.

Operating right. The interest created out of a lease that authorizes the holder of that interest to enter upon the leased lands to conduct drilling and related operations, including production of oil and gas from such lands in accordance with the terms of the lease.

Operating rights owner. A person holding operating rights in a lease issued by the United States. A leasee also may be an operating rights owner if the operating rights in a lease or portion thereof have not been conveyed to another person.

Operations. Surface disturbing activities that are conducted on a leasehold on National Forest System lands pursuant to a current approved surface use plan of operations, including but not limited to, exploration, development, and production of oil and gas resources and reclamation of surface resources.

Operator. Any person or entity, including, but not limited to, the lessee or operating rights owner, who has stated in writing to the authorized Forest officer that they are responsible under the terms and conditions of the lease for the operations conducted on the leased lands or a portion thereof.

Person. An individual, partnership, corporation, association or other legal entity.

Substantial modification. A change in lease terms or a modification, waiver, or exception of a lease stipulation that would require an environmental assessment or environmental impact statement be prepared pursuant to the National Environmental Policy Act of 1969.

Surface use plan of operations. A plan for surface use, disturbance, and reclamation.

Transfer. Any conveyance of an interest in a lease by assignment, sublease or otherwise. This definition includes the terms: Assignment which means a conveyance of all or a portion of the lessee's record title interest in a lease; and sublease which means a conveyance of a non-record interest in a lease, i.e., a conveyance of operating rights is normally a sublease and a sublease also is a subsidiary arrangement between the lessee (sublessor) and the sublessee, but a sublease does not include a transfer of a purely financial interest, such as overriding royalty interest or payment out of production, nor does it affect the relationship imposed by a lease between the lessee(s) and the United States.

Transferee. A person to whom an interest in a lease issued by the United States has been transferred.

Authorization of Occupancy Within a Leasehold

§ 228.105 - Issuance of onshore orders and notices to lessees.

(a) Onshore oil and gas orders. The Chief of the Forest Service may issue, or cosign with the Director, Bureau of Land Management, Onshore Oil and Gas Orders necessary to implement and supplement the regulations of this subpart.

(1) Surface Use Plans of Operations and Master Development Plans. Operators shall submit Surface Use Plans of Operations or Master Development Plans in accordance with Onshore Oil and Gas Order No. 1. Approval of a Master Development Plan constitutes a decision to approve Surface Use Plans of Operations submitted as a part of the Master Development Plan. Subsequently submitted Surface Use Plans of Operations shall be reviewed to verify that they are consistent with the approved Master Development Plan and whether additional NEPA documentation or consultation pursuant to the National Historic Preservation Act or the Endangered Species Act is required. If the review determines that additional documentation is required, the Forest Service will review the additional documentation or consult as appropriate and make an independent decision regarding the subsequently submitted Surface Use Plan of Operations, and notify the BLM and the operator whether the Surface Use Plan of Operations is approved.

(2) Adoption of additional onshore oil and gas orders. Additional onshore oil and gas orders shall be published in the Federal Register for public comment and codified in the CFR.

(3) Applicability of onshore oil and gas orders. Onshore Oil and Gas Orders issued pursuant to this section are binding on all operations conducted on National Forest System lands, unless otherwise provided therein.

(b) Notices to lessees, transferees, and operators. The authorized Forest officer may issue, or cosign with the authorized officer of the Bureau of Land Management, Notices to Lessees, Transferees, and Operators necessary to implement the regulations of this subpart. Notices to Lessees, Transferees, and Operators are binding on all operations conducted on the administrative unit of the National Forest System (36 CFR 200.2) supervised by the authorized Forest officer who issued or cosigned such notice.

[55 FR 10444, Mar. 21, 1990, as amended at 72 FR 10328, Mar. 7, 2007]

§ 228.106 - Operator's submission of surface use plan of operations.

(a) General. No permit to drill on a Federal oil and gas lease for National Forest System lands may be granted without the analysis and approval of a surface use plan of operations covering proposed surface disturbing activities. An operator must obtain an approved surface use plan of operations before conducting operations that will cause surface disturbance. The operator shall submit a proposed surface use plan of operations as part of an Application for a Permit to Drill to the appropriate Bureau of Land Management office for forwarding to the Forest Service, unless otherwise directed by the Onshore Oil and Gas Order in effect when the proposed plan of operations is submitted.

(b) Preparation of plan. In preparing a surface use plan of operations, the operator is encouraged to contact the local Forest Service office to make use of such information as is available from the Forest Service concerning surface resources and uses, environmental considerations, and local reclamation procedures.

(c) Content of plan. The type, size, and intensity of the proposed operations and the sensitivity of the surface resources that will be affected by the proposed operations determine the level of detail and the amount of information which the operator includes in a proposed plan of operations. However, any surface use plan of operations submitted by an operator shall contain the information specified by the Onshore Oil and Gas Order in effect when the surface use plan of operations is submitted.

(d) Supplemental plan. An operator must obtain an approved supplemental surface use plan of operations before conducting any surface disturbing operations that are not authorized by a current approved surface use plan of operations. The operator shall submit a proposed supplemental surface use plan of operations to the appropriate Bureau of Land Management office for forwarding to the Forest Service, unless otherwise directed by the Onshore Oil and Gas Order in effect when the proposed supplemental plan of operations is submitted. The supplemental plan of operations need only address those operations that differ from the operations authorized by the current approved surface use plan of operations. A supplemental plan is otherwise subject to the same requirements under this subpart as an initial surface use plan of operations.

§ 228.107 - Review of surface use plan of operations.

(a) Review. The authorized Forest officer shall review a surface use plan of operations as promptly as practicable given the nature and scope of the proposed plan. As part of the review, the authorized Forest officer shall comply with the National Environmental Policy Act of 1969, implementing regulations at 40 CFR parts 1500-1508, and the Forest Service implementing policies and procedures set forth in Forest Service Manual Chapter 1950 and Forest Service Handbook 1909.15 and shall ensure that:

(1) The surface use plan of operations is consistent with the lease, including the lease stipulations, and applicable Federal laws;

(2) To the extent consistent with the rights conveyed by the lease, the surface use plan of operations is consistent with, or is modified to be consistent with, the applicable current approved forest land and resource management plan;

(3) The surface use plan of operations meets or exceeds the surface use requirements of § 228.108 of this subpart; and

(4) The surface use plan of operations is acceptable, or is modified to be acceptable, to the authorized Forest officer based upon a review of the environmental consequences of the operations.

(b) Decision. The authorized Forest officer shall make a decision on the approval of a surface use plan of operations as follows:

(1) If the authorized Forest officer will not be able to make a decision on the proposed plan within 3 working days after the conclusion of the 30-day notice period provided for by 30 U.S.C. 226(f), the authorized Forest officer shall advise the appropriate Bureau of Land Management office and the operator as soon as such delay becomes apparent, either in writing or orally with subsequent written confirmation, that additional time will be needed to process the plan. The authorized Forest officer shall explain the reason why additional time is needed and project the date by which a decision on the plan will likely be made.

(2) When the review of a surface use plan of operations has been completed, the authorized Forest officer shall promptly notify the operator and the appropriate Bureau of Land Management office, in writing, that:

(i) The plan is approved as submitted:

(ii) The plan is approved subject to specified conditions; or,

(iii) The plan is disapproved for the reasons stated.

(c) Notice of decision. The authorized Forest officer shall give public notice of the decision on a surface use plan of operations and include in the notice that the decision is subject to appeal under 36 CFR part 214 or 215.

(d) Transmittal of decision. The authorized Forest officer shall immediately forward a decision on a surface use plan of operations to the appropriate Bureau of Land Management office and the operator. This transmittal shall include the estimated cost of reclamation and restoration (§ 228.109(a)) if the authorized Forest officer believes that additional bonding is required.

(e) Supplemental plans. A supplemental surface use plan of operations (§ 228.106(d)) shall be reviewed in the same manner as an initial surface use plan of operations.

[55 FR 10444, Mar. 21, 1990, as amended at 72 FR 10328, Mar. 7, 2007; 78 FR 33724, June 5, 2013]

§ 228.108 - Surface use requirements.

(a) General. The operator shall conduct operations on a leasehold on National Forest System lands in a manner that minimizes effects on surface resources, prevents unnecessary or unreasonable surface resource disturbance, and that is in compliance with the other requirements of this section.

(b) Notice of operations. The operator must notify the authorized Forest officer 48 hours prior to commencing operations or resuming operations following their temporary cessation (§ 228.111).

(c) Access facilities. The operator shall construct and maintain access facilities to assure adequate drainage and to minimize or prevent damage to surface resources.

(d) Cultural and historical resources. The operator shall report findings of cultural and historical resources to the authorized Forest officer immediately and, except as otherwise authorized in an approved surface use plan of operations, protect such resources.

(e) Fire prevention and control. To the extent practicable, the operator shall take measures to prevent uncontrolled fires on the area of operation and to suppress uncontrolled fires resulting from the operations.

(f) Fisheries, wildlife and plant habitat. The operator shall comply with the requirements of the Endangered Species Act of 1973 (16 U.S.C. 1531 et seq.) and its implementing regulations (50 CFR chapter IV), and, except as otherwise provided in an approved surface use plan of operations, conduct operations in such a manner as to maintain and protect fisheries, wildlife, and plant habitat.

(g) Reclamation. (1) Unless otherwise provided in an approved surface use plan of operations, the operator shall conduct reclamation concurrently with other operations.

(2) Within 1 year of completion of operations on a portion of the area of operation, the operator must reclaim that portion, unless a different period of time is approved in writing by the authorized Forest officer.

(3) The operator must:

(i) Control soil erosion and landslides;

(ii) Control water runoff;

(iii) Remove, or control, solid wastes, toxic substances, and hazardous substances;

(iv) Reshape and revegetate disturbed areas;

(v) Remove structures, improvements, facilities and equipment, unless otherwise authorized; and

(vi) Take such other reclamation measures as specified in the approved surface use plan of operations.

(h) Safety measures. (1) The operator must maintain structures, facilities, improvements, and equipment located on the area of operation in a safe and neat manner and in accordance with an approved surface use plan of operations.

(2) The operator must take appropriate measures in accordance with applicable Federal and State laws and regulations to protect the public from hazardous sites or conditions resulting from the operations. Such measures may include, but are not limited to, posting signs, building fences, or otherwise identifying the hazardous site or condition.

(i) Wastes. The operator must either remove garbage, refuse, and sewage from National Forest System lands or treat and dispose of that material in such a manner as to minimize or prevent adverse impacts on surface resources. The operator shall treat or dispose of produced water, drilling fluid, and other waste generated by the operations in such a manner as to minimize or prevent adverse impacts on surface resources.

(j) Watershed protection. (1) Except as otherwise provided in the approved surface use plan of operations, the operator shall not conduct operations in areas subject to mass soil movement, riparian areas and wetlands.

(2) The operator shall take measures to minimize or prevent erosion and sediment production. Such measures include, but are not limited to, siting structures, facilities, and other improvements to avoid steep slopes and excessive clearing of land.

§ 228.109 - Bonds.

(a) General. As part of the review of a proposed surface use plan of operations, the authorized Forest officer shall consider the estimated cost to the Forest Service to reclaim those areas that would be disturbed by operations and to restore any lands or surface waters adversely affected by the lease operations after the abandonment or cessation of operations on the lease. If at any time prior to or during the conduct of operations, the authorized Forest officer determines the financial instrument held by the Bureau of Land Management is not adequate to ensure complete and timely reclamation and restoration, the authorized Forest officer shall give the operator the option of either increasing the financial instrument held by the Bureau of Land Management or filing a separate instrument with the Forest Service in the amount deemed adequate by the authorized Forest officer to ensure reclamation and restoration.

(b) Standards for estimating reclamation costs. The authorized Forest officer shall consider the costs of the operator's proposed reclamation program and the need for additional measures to be taken when estimating the cost to the Forest Service to reclaim the disturbed area.

(c) Release of reclamation liability. An operator may request the authorized Forest officer to notify the Bureau of Land Management of reduced reclamation liability at any time after reclamation has commenced. The authorized Forest officer shall, if appropriate, notify the Bureau of Land Management as to the amount to which the liability has been reduced.

§ 228.110 - Indemnification.

The operator and, if the operator does not hold all of the interest in the applicable lease, all lessees and transferees are jointly and severally liable in accordance with Federal and State laws for indemnifying the United States for:

(a) Injury, loss or damage, including fire suppression costs, which the United States incurs as a result of the operations; and

(b) Payments made by the United States in satisfaction of claims, demands or judgments for an injury, loss or damage, including fire suppression costs, which result from the operations.

Administration of Operations

§ 228.111 - Temporary cessation of operations.

(a) General. As soon as it becomes apparent that there will be a temporary cessation of operations for a period of 45 days or more, the operator must verbally notify and subsequently file a statement with the authorized Forest officer verifying the operator's intent to maintain structures, facilities, improvements, and equipment that will remain on the area of operation during the cessation of operations, and specifying the expected date by which operations will be resumed.

(b) Seasonal shutdowns. The operator need not file the statement required by paragraph (a) of this section if the cessation of operations results from seasonally adverse weather conditions and the operator will resume operations promptly upon the conclusion of those adverse weather conditions.

(c) Interim measures. The authorized Forest officer may require the operator to take reasonable interim reclamation or erosion control measures to protect surface resources during temporary cessations of operations, including during cessations of operations resulting from seasonally adverse weather conditions.

§ 228.112 - Compliance and inspection.

(a) General. Operations must be conducted in accordance with the lease, including stipulations made part of the lease at the direction of the Forest Service, an approved surface use plan of operations, the applicable Onshore Oil and Gas Order (§ 228.105(a)), an applicable Notice to lessees, transferees, and operators (§ 228.105(b)), and regulations of this subpart.

(b) Completion of reclamation. The authorized Forest officer shall give prompt written notice to an operator whenever reclamation of a portion of the area affected by surface operations has been satisfactorily completed in accordance with the approved surface use plan of operations and § 228.108 of this subpart. The notice shall describe the portion of the area on which the reclamation has been satisfactorily completed.

(c) Compliance with other statutes and regulations. Nothing in this subpart shall be construed to relieve an operator from complying with applicable Federal and State laws or regulations, including, but not limited to:

(1) Federal and State air quality standards, including the requirements of the Clean Air Act, as amended (42 U.S.C. 1857 et seq.);

(2) Federal and State water quality standards, including the requirements of the Federal Water Pollution Control Act, as amended (33 U.S.C. 1151 et seq.);

(3) Federal and State standards for the use or generation of solid wastes, toxic substances and hazardous substances, including the requirements of the Comprehensive Environmental Response, Compensation and Liability Act, as amended, 42 U.S.C. 9601 et seq., and its implementing regulations, 40 CFR chapter I, subchapter J, and the Resource Conservation and Recovery Act, 42 U.S.C. 6901 et seq., and its implementing regulations, 40 CFR chapter I, subchapter I;

(4) The Endangered Species Act of 1973, 16 U.S.C. 1531 et seq., and its implementing regulations, 50 CFR chapter IV;

(5) The Archeological Resources Protection Act of 1979, as amended (16 U.S.C. 470aa et seq.) and its implementing regulations 36 CFR part 296;

(6) The Mineral Leasing Act of 1920, 30 U.S.C. 1981 et seq., the Mineral Leasing Act of Acquired Lands of 1947, 30 U.S.C. 351 et seq., the Federal Oil and Gas Royalty Management Act of 1982, 30 U.S.C. 1701 et seq., and their implementing regulations, 43 CFR chapter II, group 3100; and

(7) Applicable Onshore Oil and Gas Orders and Notices to Lessees and Operators (NTL's) issued by the United States Department of the Interior, Bureau of Land Management pursuant to 43 CFR chapter II, part 3160, subpart 3164.

(d) Penalties. If surface disturbing operations are being conducted that are not authorized by an approved surface use plan of operations or that violate a term or operating condition of an approved surface use plan of operations, the person conducting those operations is subject to the prohibitions and attendant penalties of 36 CFR part 261.

(e) Inspection. Forest Service officers shall periodically inspect the area of operations to determine and document whether operations are being conducted in compliance with the regulations in this subpart, the stipulations included in the lease at the direction of the Forest Service, the approved surface use plan of operations, the applicable Onshore Oil and Gas Order, and applicable Notices to Lessees, Transferees, and Operators.

§ 228.113 - Notice of noncompliance.

(a) Issuance. When an authorized Forest officer finds that the operator is not in compliance with a reclamation or other standard, a stipulation included in a lease at the direction of the Forest Service, an approved surface use plan of operation, the regulations in this subpart, the applicable onshore oil and gas order, or an applicable notice to lessees, transferees, and operators, the authorized Forest officer shall issue a notice of noncompliance.

(1) Content. The notice of noncompliance shall include the following:

(i) Identification of the reclamation requirements or other standard(s) with which the operator is not in compliance;

(ii) Description of the measures which are required to correct the noncompliance;

(iii) Specification of a reasonable period of time within which the noncompliance must be corrected;

(iv) If the noncompliance appears to be material, identification of the possible consequences of continued noncompliance of the requirement(s) or standard(s) as described in 30 U.S.C. 226(g);

(v) If the noncompliance appears to be in violation of the prohibitions set forth in 36 CFR part 261, identification of the possible consequences of continued noncompliance of the requirement(s) or standard(s) as described in 36 CFR 261.1b; and

(vi) Notification that the authorized Forest officer remains willing and desirous of working cooperatively with the operator to resolve or remedy the noncompliance.

(2) Extension of deadlines. The operator may request an extension of a deadline specified in a notice of noncompliance if the operator is unable to come into compliance with the applicable requirement(s) or standard(s) identified in the notice of noncompliance by the deadline because of conditions beyond the operator's control. The authorized Forest officer shall not extend a deadline specified in a notice of noncompliance unless the operator requested an extension and the authorized Forest officer finds that there was a condition beyond the operator's control, that such condition prevented the operator from complying with the notice of noncompliance by the specified deadline, and that the extension will not adversely affect the interests of the United States. Conditions which may be beyond the operator's control include, but are not limited to, closure of an area in accordance with 36 CFR part 261, subparts B or C, or inaccessibility of an area of operations due to such conditions as fire, flooding, or snowpack.

(3) Manner of service. The authorized Forest officer shall serve a notice of noncompliance or a decision on a request for extension of a deadline specified in a notice upon the operator in person, by certified mail or by telephone. However, if notice is initially provided in person or by telephone, the authorized Forest officer shall send the operator written confirmation of the notice or decision by certified mail.

(b) Failure to come into compliance. If the operator fails to come into compliance with the applicable requirement(s) or standard(s) identified in a notice of noncompliance by the deadline specified in the notice, or an approved extension, the authorized Forest officer shall decide whether: The noncompliance appears to be material given the reclamation requirements and other standards applicable to the lease established by 30 U.S.C. 226(g), the regulations in this subpart, the stipulations included in a lease at the direction of the Forest Service, an approved surface use plan of operations, the applicable Onshore Oil and Gas Order, or an applicable Notice to lessees, transferees, and operators; the noncompliance is likely to result in danger to public health or safety or irreparable resource damage; and the noncompliance is resulting in an emergency.

(1) Referral to compliance officer. When the operations appear to be in material noncompliance, the authorized Forest officer shall promptly refer the matter to the compliance officer. The referral shall be accompanied by a complete statement of the facts supported by appropriate exhibits. Apparent material noncompliance includes, but is not limited to, operating without an approved surface use plan of operations, conducting operations that have been suspended, failure to timely complete reclamation in accordance with an approved surface use plan of operations, failure to maintain an additional bond in the amount required by the authorized Forest officer during the period of operation, failure to timely reimburse the Forest Service for the cost of abating an emergency, and failing to comply with any term included in a lease, stipulation, or approved surface use plan of operations, the applicable onshore oil and gas order, or an applicable Notice to lessees, transferees, and operators, relating to the protection of a threatened or endangered species.

(2) Suspension of operations. When the noncompliance is likely to result in danger to public health or safety or in irreparable resource damage, the authorized Forest officer shall suspend the operations, in whole or in part.

(i) A suspension of operations shall remain in effect until the authorized Forest officer determines that the operations are in compliance with the applicable requirement(s) or standard(s) identified in the notice of noncompliance.

(ii) The authorized Forest officer shall serve decisions suspending operations upon the operator in person, by certified mail, or by telephone. If notice is initially provided in person or by telephone, the authorized Forest officer shall send the operator written confirmation of the decision by certified mail.

(iii) The authorized Forest officer shall immediately notify the appropriate Bureau of Land Management office when an operator has been given notice to suspend operations.

(3) Abatement of emergencies. When the noncompliance is resulting in an emergency, the authorized Forest officer may take action as necessary to abate the emergency. The total cost to the Forest Service of taking actions to abate an emergency becomes an obligation of the operator.

(i) Emergency situations include, but are not limited to, imminent dangers to public health or safety or irreparable resource damage.

(ii) The authorized Forest officer shall promptly serve a bill for such costs upon the operator by certified mail.

§ 228.114 - Material noncompliance proceedings.

(a) Evaluation of referral. The compliance officer shall promptly evaluate a referral made by the authorized Forest officer pursuant to § 228.113(b)(1) of this subpart.

(b) Dismissal of referral. The compliance officer shall dismiss the referral if the compliance officer determines that there is not adequate evidence to support a reasonable belief that:

(1) The operator was not in compliance with the applicable requirement(s) or standard(s) identified in a notice of noncompliance by the deadline specified in the notice, or an extension approved by the authorized Forest officer; or

(2) The noncompliance with the applicable requirement(s) or standard(s) identified in the notice of noncompliance may be material.

(c) Initiation of proceedings. The compliance officer shall initiate a material noncompliance proceeding if the compliance officer agrees that there is adequate evidence to support a reasonable belief that an operator has failed to come into compliance with the applicable requirement(s) or standard(s) identified in a notice of noncompliance by the deadline specified in the notice, or extension approved by the authorized Forest officer, and that the noncompliance may be material.

(1) Notice of proceedings. The compliance officer shall inform the lessee and operator of the material noncompliance proceedings by certified mail, return receipt requested.

(2) Content of notice. The notice of the material noncompliance proceeding shall include the following:

(i) The specific reclamation requirement(s) or other standard(s) of which the operator may be in material noncompliance;

(ii) A description of the measures that are required to correct the violation;

(iii) A statement that if the compliance officer finds that the operator is in material noncompliance with a reclamation requirement or other standard applicable to the lease, the Secretary of the Interior will not be able to issue new leases or approve new transfers of leases to the operator, any subsidiary or affiliate of the operator, or any person controlled by or under common control with the operator until the compliance officer finds that the operator has come into compliance with such requirement or standard; and

(iv) A recitation of the specific procedures governing the material noncompliance proceeding set forth in paragraphs (d) through (g) of this section.

(d) Answer. Within 30 calendar days after receiving the notice of the proceeding, the operator may submit, in person, in writing, or through a representative, an answer containing information and argument in opposition to the proposed material noncompliance finding, including information that raises a genuine dispute over the material facts. In that submission, the operator also may:

(1) Request an informal hearing with the compliance officer; and

(2) Identify pending administrative or judicial appeal(s) which are relevant to the proposed material noncompliance finding and provide information which shows the relevance of such appeal(s).

(e) Informal hearing. If the operator requests an informal hearing, it shall be held within 20 calendar days from the date that the compliance officer receives the operator's request.

(1) The compliance officer may postpone the date of the informal hearing if the operator requests a postponement in writing.

(2) At the hearing, the operator, appearing personally or through an attorney or another authorized representative, may informally present and explain evidence and argument in opposition to the proposed material noncompliance finding.

(3) A transcript of the informal hearing shall not be required.

(f) Additional procedures as to disputed facts. If the compliance officer finds that the answer raises a genuine dispute over facts essential to the proposed material noncompliance finding, the compliance officer shall so inform the operator by certified mail, return receipt requested. Within 10 days of receiving this notice, the operator may request a fact-finding conference on those disputed facts.

(1) The fact-finding conference shall be scheduled within 20 calendar days from the date the compliance officer receives the operator's request, unless the operator and compliance officer agree otherwise.

(2) At the fact-finding conference, the operator shall have the opportunity to appear with counsel, submit documentary evidence, present witnesses, and confront the person(s) the Forest Service presents.

(3) A transcribed record of the fact-finding conference shall be made, unless the operator and the compliance officer by mutual agreement waive the requirement for a transcript. The transcript will be made available to the operator at cost upon request.

(4) The compliance officer may preside over the fact-finding conference or designate another authorized Forest officer to preside over the fact-finding conference.

(5) Following the fact-finding conference, the authorized Forest officer who presided over the conference shall promptly prepare written findings of fact based upon the preponderance of the evidence. The compliance officer may reject findings of fact prepared by another authorized Forest officer, in whole or in part, if the compliance officer specifically determines that such findings are arbitrary and capricious or clearly erroneous.

(g) Dismissal of proceedings. The compliance officer shall dismiss the material noncompliance proceeding if, before the compliance officer renders a decision pursuant to paragraph (h) of this section, the authorized Forest officer who made the referral finds that the operator has come into compliance with the applicable requirements or standards identified in the notice of proceeding.

(h) Compliance officer's decision. The compliance officer shall base the decision on the entire record, which shall consist of the authorized Forest officer's referral and its accompanying statement of facts and exhibits, information and argument that the operator provided in an answer, any information and argument that the operator provided in an informal hearing if one was held, and the findings of fact if a fact-finding conference was held.

(1) Content. The compliance officer's decision shall state whether the operator has violated the requirement(s) or standard(s) identified in the notice of proceeding and, if so, whether that noncompliance is material given the requirements of 30 U.S.C. 226(g), the stipulations included in the lease at the direction of the Forest Service, the regulations in this subpart or an approved surface use plan of operations, the applicable onshore oil and gas order, or an applicable notice to lessees, transferees, and operators. If the compliance officer finds that the operator is in material noncompliance, the decision also shall:

(i) Describe the measures that are required to correct the violation;

(ii) Apprise the operator that the Secretary of the Interior is being notified that the operator has been found to be in material noncompliance with a reclamation requirement or other standard applicable to the lease; and

(iii) State that the decision is the final administrative determination of the Department of Agriculture.

(2) Service. The compliance officer shall serve the decision upon the operator by certified mail, return receipt requested. If the operator is found to be in material noncompliance, the compliance officer also shall immediately send a copy of the decision to the appropriate Bureau of Land Management office and to the Secretary of the Interior.

(i) Petition for withdrawal of finding. If an operator who has been found to be in material noncompliance under the provisions of this section believes that the operations have subsequently come into compliance with the applicable requirement(s) or standard(s) identified in the compliance officer's decision, the operator may submit a written petition requesting that the material noncompliance finding be withdrawn. The petition shall be submitted to the authorized Forest officer who issued the operator the notice of noncompliance under § 228.113(a) of this subpart and shall include information or exhibits which shows that the operator has come into compliance with the requirement(s) or standard(s) identified in the compliance officer's decision.

(1) Response to petition. Within 30 calendar days after receiving the operator's petition for withdrawal, the authorized Forest officer shall submit a written statement to the compliance officer as to whether the authorized Forest officer agrees that the operator has come into compliance with the requirement(s) or standard(s) identified in the compliance officer's decision. If the authorized Forest officer disagrees with the operator, the written statement shall be accompanied by a complete statement of the facts supported by appropriate exhibits.

(2) Additional procedures as to disputed material facts. If the compliance officer finds that the authorized Forest officer's response raises a genuine dispute over facts material to the decision as to whether the operator has come into compliance with the requirement(s) or standard(s) identified in the compliance officer's decision, the compliance officer shall so notify the operator and authorized Forest officer by certified mail, return receipt requested. The notice shall also advise the operator that the fact finding procedures specified in paragraph (f) of this section apply to the compliance officer's decision on the petition for withdrawal.

(3) Compliance officer's decision. The compliance officer shall base the decision on the petition on the entire record, which shall consist of the operator's petition for withdrawal and its accompanying exhibits, the authorized Forest officer's response to the petition and, if applicable, its accompanying statement of facts and exhibits, and if a fact-finding conference was held, the findings of fact. The compliance officer shall serve the decision on the operator by certified mail.

(i) If the compliance officer finds that the operator remains in violation of requirement(s) or standard(s) identified in the decision finding that the operator was in material noncompliance, the decision on the petition for withdrawal shall identify such requirement(s) or standard(s) and describe the measures that are required to correct the violation(s).

(ii) If the compliance officer finds that the operator has subsequently come into compliance with the requirement(s) or standard(s) identified in the compliance officer's decision finding that the operator was in material noncompliance, the compliance officer also shall immediately send a copy of the decision on the petition for withdrawal to the appropriate Bureau of Land Management office and notify the Secretary of the Interior that the operator has come into compliance.

(j) List of operators found to be in material noncompliance. The Deputy Chief, National Forest System, shall compile and maintain a list of operators who have been found to be in material noncompliance with reclamation requirements and other standards as provided in 30 U.S.C. 226(g), the regulations in this subpart, a stipulation included in a lease at the direction of the Forest Service, or an approved surface use plan of operations, the applicable onshore oil and gas order, or an applicable notice to lessees, transferees, and operators, for a lease on National Forest System lands to which such standards apply. This list shall be made available to Regional Foresters, Forest Supervisors, and upon request, members of the public.

§ 228.115 - Additional notice of decisions.

(a) The authorized Forest officer shall promptly post notices provided by the Bureau of Land Management of:

(1) Competitive lease sales which the Bureau plans to conduct that include National Forest System lands;

(2) Substantial modifications in the terms of a lease which the Bureau proposes to make for leases on National Forest System lands; and

(3) Applications for permits to drill which the Bureau has received for leaseholds located on National Forest System lands.

(b) The notice shall be posted at the offices of the affected Forest Supervisor and District Ranger in a prominent location readily accessible to the public.

(c) The authorized Forest officer shall keep a record of the date(s) the notice was posted in the offices of the affected Forest Supervisor and District Ranger.

(d) The posting of notices required by this section are in addition to the requirements for public notice of decisions provided in § 228.104(d) (Notice of decision) and § 228.107(c) (Notice of decision) of this subpart.

§ 228.116 - Information collection requirements.

(a) Sections containing information requirements. The following sections of this subpart contain information requirements as defined in 5 CFR part 1320 and have been approved for use by the Office of Management and Budget:

(1) Section 228.104(a) Requests to Modify, Waive, or Grant Exceptions to Leasing Stipulations;

(2) Section 228.106 (a), (c), and (d) Submission of Surface Use Plan of Operations;

(3) Section 228.109(c) Request for Reduction in Reclamation Liability after Reclamation;

(4) Section 228.111(a) Notice of Temporary Cessation of Operations;

(5) Section 228.113(a)(2) Extension of Deadline in Notice of Noncompliance; and

(6) Section 228.114 (c) through (i) Material Noncompliance Proceedings.

(b) OMB control number. The information requirements listed in paragraph (a) of this section have been assigned OMB Control No. 0596-0101.

(c) Average estimated burden hours. (1) The average burden hours per response are estimated to be:

(i) 5 minutes for the information requirements in § 228.104(a) of this subpart;

(ii) No additional burden hours required to meet the information requirements in § 228.106 (a), (c), and (d) of this subpart;

(iii) 10 minutes for the information requirements in § 228.109(c) of this subpart;

(iv) 10 minutes for the information requirements in § 228.111(a) of this subpart;

(v) 5 minutes for the information requirements in § 228.113(a)(2) of this subpart; and

(vi) 2 hours for the information requirements in § 228.114 (c) through (i) of this subpart.

(2) Send comments regarding the burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to Chief (2800), Forest Service, USDA, P.O. Box 96090, Washington, DC 20090-6090 and to the Office of Information and Regulatory Affairs, Office of Management and Budget, Washington, DC 20503.