Collapse to view only § 25.703 - Claims payable.
- § 25.701 - Scope.
- § 25.703 - Claims payable.
- § 25.705 - Claims not payable.
- § 25.707 - Time limitation on claims.
- § 25.709 - Assessment limitation on claims.
§ 25.701 - Scope.
This subpart prescribes the requirements for the administrative settlement of claims under Article 139, Uniform Code of Military Justice, 10 U.S.C. 939, against military members of the Coast Guard for damage to property willfully caused by them or loss of property wrongfully taken by them.
§ 25.703 - Claims payable.
A claim for damage to or loss of real or personal property caused by a military member of the Coast Guard is payable under this subpart when the damage or loss results from:
(a) Willful or intentional acts;
(b) Wrongful taking; or
(c) Riotous, violent, and reckless conduct or acts of depredation by an individual or group that evidences willfulness.
§ 25.705 - Claims not payable.
A claim is not payable under this subpart if it:
(a) Is for death or personal injury;
(b) Results wholly or partly from the grossly negligent, or reckless act of the claimant, claimant's agent or employee;
(c) Is a subrogated claim;
(d) Is for damage to or loss of property owned by the United States or property of a Nonappropriated Fund Activity;
(e) Results from negligence;
(f) Is for indirect or remote damages;
(g) Is for damage to or loss of property resulting from the act or omission of a member of the Coast Guard acting within the scope of the member's employment;
(h) Extends to damage or loss that results from the owner's failure to mitigate damages; or
(i) Has been paid by a third party.
§ 25.707 - Time limitation on claims.
A claim may be settled only if presented within 90 days after it accrues unless good cause is shown for the delay.
§ 25.709 - Assessment limitation on claims.
A claim is permitted in any amount; however, this subpart prohibits any assessment that exceeds one-half of one month's basic pay against the pay of any offender.